Yu Bunuan v. Marcaida

G.R. No. L-3457 · 1908-03-02 · J. CARSON, J.: · Primary: Civil; Secondary: Commercial
REITERATION

Facts

The Antecedents: Plaintiffs-appellees, Yu Bunuan, Chu Beco, and Co Narciso, partners trading under the firm name of Vicente Co-chico and Co., filed an action to recover P3,830 from defendant-appellant, Orestes Marcaida. The sum represented a balance due for work done and materials furnished. The complaint contained two causes of action: one for work done and materials furnished in constructing two cottages under a contract between the defendant and the deceased Vicente Co-chico, and another for work and materials furnished independently of that contract. Procedural History: The trial court rendered judgment in favor of the plaintiffs for P1,551.20, with interest at 6% per annum and costs. The defendant excepted to this judgment and appealed. The Petition: The defendant-appellant raised several assignments of error, including errors in the court's findings of fact, overruling of the demurrer to the complaint, refusal to allow a claim for damages due to delay, and the rendition of judgment against him.

Issue(s)

Whether the plaintiffs, as an unregistered partnership, had the legal capacity to sue. Whether the plaintiffs, as assignees of a contract, could maintain an action without the express consent of the defendant to the assignment. Whether the defendant was entitled to damages for the delay in the completion of the cottages. Whether the trial court erred in its findings of fact and in rendering judgment against the defendant.

Ruling

The Supreme Court affirmed the judgment of the trial court, ordering the defendant-appellant to pay the plaintiffs-appellees the sum of P1,551.20, with interest and costs.

Ratio Decidendi

On the legal capacity to sue of an unregistered partnership: The Court held that while an action could not be brought in the name of the partnership as such, the individual members of an unregistered partnership may maintain a joint action on a contract. The complaint was filed in the names of the individual partners, who were trading under the firm name, thus satisfying the requirement for legal capacity to sue. This aligns with established jurisprudence that permits individual partners to sue collectively. On the assignment of contract rights without explicit assent: The Court found that the original contractor, Co-chico, had ceded his interest in the contract to the partnership. Although the defendant contended that he was not notified of or did not assent to this conveyance, and that the contract was personal, the Court noted that the defendant had conclusively proven to have accepted the work done when completed. Furthermore, the defendant continued in possession of the cottages and enjoyed the rents and profits therefrom with full knowledge of the assignment. This acceptance and continued enjoyment of the benefits of the contract, with knowledge, estopped the defendant from denying the validity of the assignment or the right of the partnership to recover the balance due. It was deemed irrelevant to the defendant whether payment was made to Co-chico or to his order, provided no set-off or counterclaim was lost. On damages for delay: The defendant sought damages for the delay in completing the cottages beyond the stipulated time. However, the evidence showed that changes were made to the plans and specifications at the instance of the defendant after the contract was signed. No agreement was made regarding the time for completion of the modified work. The Court ruled that since the changes were made at the defendant's request, it was proper for the trial court to refuse to apply the penal provisions of the original contract to the modified contract. The defendant could not claim damages for delays caused by modifications he himself requested without stipulating new deadlines. On errors in findings of fact and judgment: The Court reviewed the evidence, acknowledging that it was contradictory. However, after a thorough review of the entire record, the Court found no justification to hold that the facts upon which the trial court based its judgment were not sustained by the weight of the evidence. Therefore, the assignments of error pertaining to factual findings and the final judgment were deemed without merit.

Main Doctrine

An unregistered partnership may maintain a joint action through its individual members. Acceptance of work done under a contract, with full knowledge of the assignment of rights, obligates the party to pay the agreed price, even if the assignment was not explicitly assented to. Modifications to a contract at the request of a party, without agreement on new timelines, preclude the application of original penal provisions for delays.

Access audio review, related cases, codal links, and more.

Open LexMatePH →