Abesamis v. Woodcraft Works, Ltd.

G.R. No. L-18916 · 1969-11-28 · J. MAKALINTAL, J.: · Primary: Commercial; Secondary: Civil
REITERATION

Facts

The Antecedents: Plaintiff Jose Abesamis, doing business as East Samar Lumber Mills, entered into two contracts with defendant Woodcraft Works, Ltd. The first contract, dated November 8, 1950, was for the purchase of 300,000 board feet of logs, but only a small portion was delivered due to weather and the defendant's failure to send vessels. This contract was cancelled, and the parties entered into a new one on January 22, 1951, for 1,700,000 board feet of logs, with P9,000.00 in advances transferred from the first contract. The new contract stipulated shipment before the end of July 1951, not commencing earlier than April, with partial shipments allowed. Only two shipments were made, totaling 462,657 board feet. Procedural History: On September 13, 1951, the plaintiff filed an action for rescission of the January 22, 1951 contract and for damages amounting to P155,000.00 in the Court of First Instance of Leyte. The defendant denied the allegations and filed counterclaims. The lower court rendered judgment rescinding the contract, ordering the defendant to pay P145,623.03 for actual damages, P50,000.00 for loss of credit, and P5,000.00 for attorney's fees. The Appeal: The defendant appealed to the Supreme Court, arguing that the lower court erred in finding that Woodcraft Works, Ltd. was obligated to send the boat, that the plaintiff had sufficient logs, that the appellant failed to comply with the contract, and in granting damages to the appellee while not granting damages to the appellant.

Issue(s)

Whether the defendant-appellant was obligated to furnish the vessel for the shipment of logs. Whether the plaintiff-appellee had sufficient stock of logs to cover the contract by July 31, 1951. Whether the defendant-appellant breached the contract by failing to comply with its terms and conditions. Whether the plaintiff-appellee is entitled to damages, and if so, in what amount. Whether the defendant-appellant is entitled to damages and recovery of money.

Ruling

The Supreme Court affirmed the rescission of the contract and modified the award of damages. The defendant-appellant, Woodcraft Works, Ltd., was ordered to pay the plaintiff-appellee an aggregate sum of P69,685.26 by way of damages, plus P5,000.00 as attorney's fees. The P50,000.00 awarded for loss of credit was eliminated.

Ratio Decidendi

On Issue 1: Whether the defendant-appellant was obligated to furnish the vessel for the shipment of logs. The Court held that the contract, while not expressly stating who should furnish the vessel, contained provisions that clearly implied this obligation devolved upon the appellant. These provisions included the appellant's responsibility for Bureau of Forestry inspection charges and Philippine Government wharfage fees, as well as stipulations regarding the dispatch of the ship, loading rates, and demurrage. The Court reasoned that these terms would be of little concern to the appellant if the appellee were the one to provide the vessel. Furthermore, the contemporaneous and subsequent acts of the parties, specifically the appellant furnishing vessels in the two prior shipments and the exchange of telegraphic communications regarding vessel arrivals, unequivocally pointed to the appellant's obligation. The appellant's own witness testimony explaining difficulties in securing vessels further supported this implied obligation. On Issue 2: Whether the plaintiff-appellee had sufficient stock of logs to cover the contract by July 31, 1951. The Court found that the appellee had sufficient logs. While a Bureau of Forestry certificate indicated a lower production, the appellee satisfactorily explained this discrepancy by stating that logs were only reported to the Bureau of Forestry upon shipment to avoid paying forest charges on unpaid timber. The appellee testified to having 1,300,000 board feet of logs available by the end of July 1951, with 800,000 ready for loading. Evidence from a lumber inspector also indicated substantial quantities of graded and ungraded logs available, and continued logging operations after the last inspection supported the appellee's claim of sufficient stock by the contract deadline. On Issue 3: Whether the defendant-appellant breached the contract by failing to comply with its terms and conditions. The Court ruled that the appellant breached the contract. The primary breach was the failure to furnish vessels as implied by the contract and demonstrated by the parties' conduct. This failure led to subsequent losses for the appellee. The Court also noted that the appellant waived the benefit of the period when it assured the appellee of a vessel's arrival on a specific date (June 25, 1951), but then failed to deliver without satisfactory explanation, constituting another breach. The appellant's failure to send a vessel by the end of July 1951, despite the appellee having sufficient logs, was also deemed a breach without evidence of circumstances beyond the appellant's control. On Issue 4: Whether the plaintiff-appellee is entitled to damages, and if so, in what amount. The Court affirmed the award of actual damages, but modified the total amount. The appellee was entitled to damages for the 60,000 board feet of logs lost due to the non-arrival of the "SS ALBAY" on June 25, 1951 (valued at P7,685.26), and for the 800,000 board feet destroyed by marine borers by the end of July 1951 (valued at P62,000.00). These losses directly resulted from the appellant's breaches. However, the claim for P50,000.00 for loss of credit was eliminated due to insufficient evidence, as mere demands for payment from creditors do not automatically prove loss of credit. The P5,000.00 for attorney's fees was maintained. On Issue 5: Whether the defendant-appellant is entitled to damages and recovery of money. The Court found no basis for the defendant-appellant's claim for damages or recovery of money. The appellant's own failures and breaches of contract were the cause of the dispute and the losses incurred. The contract was rescinded due to the appellant's non-performance, and the appellant was ordered to pay damages to the appellee, not the other way around. Therefore, the appellant's counterclaims were dismissed.

Main Doctrine

The Supreme Court affirmed the rescission of a contract and awarded damages, holding that the defendant-appellant breached its obligation to furnish vessels for log shipment. The Court found that the contract's provisions on fees, dispatch of ships, and demurrage, along with the parties' conduct, implied an obligation on the appellant to provide the vessels. Furthermore, the Court clarified that in reciprocal obligations with a term, no party incurs delay before the period expires, and losses occurring before such time, without delay, are borne by the party suffering them, unless the period is waived.

Access audio review, related cases, codal links, and more.

Open LexMatePH →