Chan Suanco v. Alonso

G.R. No. L-4709 · 1909-11-29 · J. JOHNSON, J.: · Primary: Civil; Secondary: Commercial
REITERATION

Facts

The Antecedents: The plaintiff initiated an action to recover the balance due on a building contract, including P961 as the balance and P1,067.56 for labor and material for changes and additions requested by the defendant. Procedural History: The Court of First Instance initially found P2,028.56 due to the plaintiff. Subsequently, the defendant moved for a reopening or new trial, which was granted. After a second trial, the court rendered a judgment for P674.74 in favor of the plaintiff. Both parties appealed this judgment. The Petition: The defendant appealed, assigning errors related to the court's holding that he could not deny the building of the house according to the contract, the failure to order the plaintiff to finish the work or pay its equitable value, and the dismissal of the complaint. The plaintiff also appealed, arguing the court erred in reopening the trial without annulling the initial judgment and without a proper motion.

Issue(s)

Whether the defendant, by taking possession of the house before completion and without specific objection at that time, acknowledged substantial compliance with the building contract. Whether the court erred in granting a new trial under Section 145 of the Code of Civil Procedure.

Ruling

The judgment of the lower court is affirmed. Judgment is to be entered against the defendant and in favor of the plaintiff for the sum of P674.74, with interest at 6% from February 28, 1907, and costs.

Ratio Decidendi

On the issue of acceptance and denial of the contract: The Court held that the defendant's act of taking possession of the house before its completion, without making specific objections at that time regarding the work or materials, constituted an acknowledgment that the work had been performed substantially as agreed upon in the contract. This express acceptance, without protest, precludes the defendant from later raising objections about the labor or material furnished, as established in cases like Campbell vs. Behn, Meyer & Co. and Naval vs. Benavides. The Court noted that this acceptance would not prevent objections regarding hidden defects, but no such defects were raised by the defendant. The only objection made at the time of taking possession was that the construction was not fully completed, and the court found the value of this incomplete work to be P286.26, which was deducted from the balance due. On the issue of granting a new trial: The Court found no sufficient reason to declare that the lower court abused its discretion in granting a new trial. The conditions under which a judge may grant a new trial are broad, allowing it upon motion of the parties or upon the court's own motion if excessive damages are found, the evidence is insufficient, or the decision is against the law. While the specific ground for granting the new trial was not disclosed in the record, the plaintiff's appeal did not provide a compelling argument for an abuse of discretion. Therefore, the Court affirmed the judgment rendered after the new trial.

Main Doctrine

The acceptance of a building or work without protest or objection, with respect to the labor or material furnished, constitutes an acknowledgment that the work has been performed substantially as agreed upon in the contract, precluding the owner from subsequently raising questions about the work or material, unless hidden defects not discoverable upon casual examination exist.

Access audio review, related cases, codal links, and more.

Open LexMatePH →