Lichauco v. Cho-Chun-Chac

G.R. No. L-4877 · 1911-03-31 · J. CARSON, J.: · Primary: Civil; Secondary: Commercial
REITERATION

Facts

The Antecedents: The case involves a dispute arising from a contract for the construction of launches. The plaintiff, Crisanto Lichauco, sought to recover sums related to the construction of these launches, which were undertaken at the expense of the defendant, Cho-Chun-Chac, pursuant to a prior Supreme Court judgment dated November 18, 1900. Procedural History: The prior Supreme Court judgment of November 18, 1900, had authorized the plaintiff to have the launches constructed at the defendant's expense and to recoup any losses incurred due to expenditures exceeding the contract price. The present action was filed to recover specific amounts allegedly due to the plaintiff based on this prior judgment and the execution of the contract. The Appeal: The defendant appealed the judgment of the lower court, which had awarded the plaintiff specific sums. The Supreme Court reviewed the case, considering the pleadings and evidence, to determine the correctness of the lower court's awards, particularly concerning the difference between actual and contract prices for executed and unexecuted portions of the contract.

Issue(s)

Whether the plaintiff is entitled to recover the difference between the actual cost price and the contract price of the launch actually constructed. Whether the plaintiff is entitled to recover the difference between the contract price and the estimated cost of constructing two other launches that were authorized but not executed. Whether the plaintiff is entitled to recover the sum advanced over and above the contract price for the single launch actually constructed.

Ruling

The Supreme Court modified the judgment of the lower court. It affirmed the award for the difference between the actual cost and contract price of the single launch actually constructed. It reversed the award for the difference between the contract price and the estimated cost of the two unexecuted launches. It also reversed the denial of the plaintiff's right to recover the sum advanced over and above the contract price for the single launch actually constructed. The dispositive portion ordered judgment in favor of the plaintiff for P6,719.16, with legal interest.

Ratio Decidendi

On Issue 1: The Court affirmed the lower court's award for the sum of P1,824.16, representing the difference between the actual cost and the contract price of the launch that was actually constructed. The evidence satisfactorily established that this launch was constructed for the plaintiff at the defendant's expense, and the cost exceeded the original contract price by this amount. The defendant could not deny the binding effect of the prior Supreme Court judgment of November 18, 1900, which authorized such recovery. On Issue 2: The Court reversed the lower court's award of P11,900, which represented the difference between the contract price and the estimated cost of constructing two other launches. The prior Supreme Court judgment authorized the construction of these launches at the defendant's expense but did not provide for damages based on estimated costs if they were not actually executed. The plaintiff, having elected to sue for specific performance, could not arbitrarily abandon the contract and convert the judgment into one for damages based on estimates rather than actual losses. On Issue 3: The Court reversed the lower court's denial of the plaintiff's right to recover P4,895, which was advanced by the plaintiff over and above the contract price for the single launch actually constructed. The evidence satisfactorily established the justice of this claim and the amount of the advance. The Court found no reason why the plaintiff should not have recovered this amount in the present action, as it was directly related to the executed portion of the contract and the settlement of his indebtedness, thus avoiding further litigation.

Main Doctrine

The Supreme Court affirmed that a party cannot unilaterally convert a judgment for specific performance into a judgment for damages. The Court held that the plaintiff, having elected to sue for specific performance, could not arbitrarily abandon the contract and seek damages based on estimated costs. However, the Court allowed recovery for advances made by the plaintiff over and above the contract price for the single launch actually constructed, provided the claim and the amount of advance were satisfactorily established.

Access audio review, related cases, codal links, and more.

Open LexMatePH →