Sarmiento v. Court of Appeals

G.R. No. L-83138 October 17, 1989 · 1989-10-17 · J. PARAS, J.: · Primary: Commercial; Secondary: Civil
REITERATION

Facts

The Antecedents: Mass Integrated Group, represented by Amalio L. Sarmiento, contracted with the Ministry of Public Works and Highways (MPWH) for the Mangahan Floodway Project (Phase B). Sarmiento engaged Hercon, Inc. as a subcontractor. An agreement stipulated that Hercon, Inc. would participate in 70% of Sarmiento's collections from MPWH, including escalation on earthworks, and for dredging works, receive P5.00 per cubic meter plus 40% of any price escalation payments from MPWH. Procedural History: Hercon, Inc. stopped working on September 19, 1982, claiming Sarmiento failed to pay progress billings and its share in price escalation costs. Hercon, Inc. filed a complaint for P3,846,075.86 and P2,301,027.83. Sarmiento counterclaimed for damages, alleging breach of contract due to abandonment and malicious filing of suit. The Regional Trial Court (RTC) ruled in favor of Sarmiento, ordering Hercon, Inc. to pay P7,370,450.31 for defective works and operational costs, P500,000.00 for moral damages, P200,000.00 for exemplary damages, and P300,000.00 for attorney's fees. The Court of Appeals (CA) modified the decision, upholding actual damages of P7,370,450.31 for Sarmiento but disallowing moral and exemplary damages and attorney's fees, while awarding Hercon, Inc. P6,147,103.70 for price escalation. The CA offset these amounts, leaving P1,223,346.61 due to Sarmiento. The Petition: Both parties filed petitions for review. Sarmiento sought to reinstate the RTC's award of damages and attorney's fees and to disallow price escalation payment to Hercon, Inc. Hercon, Inc. sought to reinstate its award for actual damages.

Issue(s)

Whether or not Hercon, Inc. breached its contract with Sarmiento with respect to the Mangahan Floodway Project (Phase B). Whether or not Sarmiento is entitled to the damages awarded by the trial court. Whether or not Hercon, Inc. is entitled to the payment of price escalation costs in the amount of P6,147,103.70.

Ruling

The Supreme Court reinstated the decision of the Regional Trial Court in its entirety, setting aside the decision of the Court of Appeals. Hercon, Inc. was ordered to pay Amalio L. Sarmiento P7,370,450.31 for defective works and operational costs, P500,000.00 for moral damages, P200,000.00 for exemplary damages, and P300,000.00 for attorney's fees, plus costs. Other claims and counterclaims were dismissed.

Ratio Decidendi

On whether Hercon, Inc. breached its contract with Sarmiento: The Court found that Hercon, Inc. breached its contract with Sarmiento. The Court of Appeals itself found that Hercon, Inc. abandoned the project and that there were defects and deficiencies in its works. Hercon, Inc. attempted to justify its work stoppage by claiming Sarmiento failed to pay and issued bouncing checks. However, documentary evidence proved that Sarmiento was up to date with payments. The checks were postdated and issued in advance to encourage Hercon, Inc. to resume work, but Sarmiento ordered payment stopped when Hercon, Inc. refused. Hercon, Inc. also ignored requests for a conference to reconcile accounts, which could have resolved payment issues. On whether Sarmiento is entitled to the damages awarded by the trial court: The Court held that Sarmiento is entitled to the damages awarded by the trial court. The breach of contract by Hercon, Inc. was tainted with bad faith, as evidenced by its unjustified abandonment of the project. Sarmiento's testimony detailed the tremendous negative impact on his reputation, standing with banks and fellow contractors, and the eventual termination of his contract with MPWH due to Hercon, Inc.'s failure to complete its undertaking. The Court found the amounts awarded for actual, moral, and exemplary damages, as well as attorney's fees, to be reasonable given the circumstances and Sarmiento's ordeal. On whether Hercon, Inc. is entitled to the payment of price escalation costs: The Court ruled that Hercon, Inc. is not entitled to price escalation costs. The Court of Appeals' award was based solely on a summary of claims (Exh. Q) and testimony, without sufficient evidence to substantiate the claim or allow for computation and segregation from collections made by Sarmiento. The trial court's factual finding, adopted by the CA, was that Hercon, Inc. failed to present clear or direct evidence to show its entitlement to escalation costs or how such a claim could be computed and segregated from the various collections made by Sarmiento from MPWH, especially since Hercon, Inc. was only one of several subcontractors. The Court emphasized that judgments must conform to both pleadings and proof, and Hercon, Inc. failed to provide the necessary evidence.

Main Doctrine

The Court of Appeals committed reversible error in eliminating the damages awarded by the trial court to Sarmiento and in holding the latter liable for price escalation costs to Hercon, Inc. despite its own finding that the latter abandoned the project and that there were defects and deficiencies in its works in the project. Hercon, Inc.'s contractual breach was tainted with bad faith.

Access audio review, related cases, codal links, and more.

Open LexMatePH →