D.M. Consunji, Inc. v. Commission on Audit

G.R. No. 94913 · 1991-07-23 · J. GUTIERREZ, JR., J.: · Primary: Taxation; Secondary: Commercial
REITERATION

Facts

The Antecedents: This case concerns a contract awarded by the Metropolitan Waterworks and Sewerage System (MWSS) to D.M. Consunji, Inc. for the rehabilitation of the Tondo Pump Station. The core dispute revolves around a price escalation payment made to D.M. Consunji, Inc. The Corporate Auditor of MWSS disallowed a portion of this payment, amounting to P3,900,605.45, alleging it was an overpayment. The auditor contended that the price escalation should have been calculated from October 1, 1982, while D.M. Consunji, Inc. argued it should be reckoned from May 1981, the date of the bidding. Procedural History: The Corporate Auditor of MWSS issued a Notice of Audit Disallowance No. FA-001 on March 7, 1988, disallowing P3,900,605.45 in price escalation payments and demanding reimbursement from D.M. Consunji, Inc. The company appealed this disallowance to the Commission on Audit (COA), maintaining that no overpayment occurred. On August 18, 1989, the COA dismissed the appeal, ruling that the contract was negotiated, not bidded, and that the escalation should be calculated from October 1, 1982. A subsequent motion for reconsideration was also denied by the COA on July 24, 1990. The Petition: D.M. Consunji, Inc. filed a petition for review with the Supreme Court, seeking to set aside the decisions of the Commission on Audit. The petitioner argues that Contract No. PS-1 was a bidded contract, not a negotiated one, and that the price escalation should be reckoned from May 1981, the date of bidding, as per existing rules and regulations governing government infrastructure projects. The petitioner asserts that the escalation from May 1981 to September 1982 was already incorporated into the base contract price, and subsequent escalations should also be calculated from May 1981, not October 1, 1982, as determined by the COA. The central contention is that the COA committed grave abuse of discretion in its interpretation of the contract and the applicable laws regarding price escalation.

Issue(s)

Whether Contract No. PS-1 is a bidded contract or a negotiated contract. Whether the petitioner was overpaid in the amount of P3,900,605.45 representing price escalation.

Ruling

The Supreme Court granted the petition, reversed and set aside the decisions of the Commission on Audit and the Notice of Audit Disallowance. It ruled that Contract No. PS-1 is a bidded contract and that the COA committed grave abuse of discretion in requiring reimbursement of the price escalation payment.

Ratio Decidendi

On whether Contract No. PS-1 is a bidded contract or a negotiated contract: The Court held that Contract No. PS-1 is a bidded contract. Presidential Decree No. 1594 and its implementing rules prioritize public bidding for construction projects, allowing negotiated contracts only in exceptional cases after the failure of public bidding. The rules clearly state that a negotiated contract ensues only after the failure of the first and second biddings, with proper advertisement for the second bidding. In this case, there was no evidence of a second bidding being conducted or advertised. The initial bidding had the lowest bidder disqualified and the second lowest bidder withdraw, paving the way for the offer to the petitioner, the highest bidder. The MWSS General Manager's letter offering the contract explicitly referred to the bidding and stated that the project would be rebid if the petitioner could not perform. Furthermore, negotiations on contract details do not automatically convert a bidded contract into a negotiated one, especially when Section 3 of IB 2.5 authorizes negotiations with a higher bidder when lower bids are unacceptable. The MWSS itself, in a letter from its Administrator, acknowledged Contract No. PS-1 as a bidded contract. On whether the petitioner was overpaid in the amount of P3,900,605.45 representing price escalation: The Court ruled that the COA committed grave error in reckoning the date of price escalation from October 1, 1982, as provided in the contract, instead of May 27, 1981, the date of bidding. While the contract stipulated October 1, 1982, for succeeding escalations, this provision must be read in conjunction with existing laws and regulations, which form part of the contract. COA Circular No. 267 and the Implementing Rules and Regulations of P.D. 1594 clearly state that for bidded contracts, price escalation shall be reckoned from the month of bidding. The petitioner's explanation that the escalation from May 1981 to September 1982 was already incorporated into the base contract price, with October 1, 1982, being the date for subsequent escalations, was supported by the MWSS's own letter. Therefore, reckoning the Allowable Escalation Rate from the bidding date of May 27, 1981, was consistent with the law and the contract's intent, as the price escalation effectively started from that date. The COA's interpretation contravened the principle that existing laws form part of a contract and thus constituted grave abuse of discretion.

Main Doctrine

The Commission on Audit committed grave abuse of discretion in disallowing a price escalation payment by reckoning the date for price escalation from the contract date instead of the bidding date, as mandated by existing laws and regulations for bidded government infrastructure contracts, especially when the contract itself incorporated prior escalations from the bidding date.

Access audio review, related cases, codal links, and more.

Open LexMatePH →