Genaro R. Reyes Construction, Inc. v. Court of Appeals

G.R. No. 108718 · 1994-07-14 · J. MELO, J.: · Primary: Civil; Secondary: Administrative Law, Contracts
REITERATION

Facts

The Antecedents: Petitioners, Genaro R. Reyes Construction, Inc. (GGRCI) and Universal Dockyard Ltd. (UDL), entered into a contract with the Department of Public Works and Highways (DPWH) for the construction of flood control facilities and land improvement works for the Lower Agusan Development Project. The joint venture, of which petitioners were part, submitted the lowest bid, significantly below the Approved Government Estimate. Subsequently, DPWH issued a Notice to Proceed. However, DPWH Project Engineers recommended the termination of the contract due to alleged negative slippage of 9.50% as of April 23, 1992, a figure later revised to 9.8%. Procedural History: Despite the reported negative slippage being below the 15% threshold stipulated in Presidential Decree No. 1870 for contract termination, DPWH issued a notice of termination to the petitioners. The petitioners sought reconsideration, highlighting that the delay was partly attributable to the government's failure to secure the necessary right-of-way and other issues. When their request was denied, they filed a case with the Regional Trial Court (RTC) seeking injunctions to prevent the termination and rebidding of the project. The RTC denied their application for a temporary restraining order and preliminary injunction, citing Presidential Decree No. 1818, which prohibits courts from issuing such injunctions in cases involving infrastructure projects. The petitioners then elevated the matter to the Court of Appeals (CA), which affirmed the RTC's decision. The CA also denied their subsequent motion for reconsideration. The Petition: Petitioners now seek relief from this Court through a petition for certiorari and prohibition, arguing that the Court of Appeals committed grave abuse of discretion in affirming the RTC's denial of injunctive relief. They contend that the termination of their contract was unlawful as the negative slippage did not reach the 15% threshold mandated by law, and that significant delays were caused by the DPWH's own shortcomings, including right-of-way acquisition issues and internal coordination problems. Petitioners further argue that Presidential Decree No. 1818 does not apply as the relief sought is not to stop the project's implementation but to compel the DPWH to proceed with their contract, asserting that the termination constitutes a violation of their property rights and public interest, especially considering the potential financial loss to the government if the project is awarded to a significantly higher bidder.

Issue(s)

Whether the Court of Appeals committed a reversible error in affirming the Regional Trial Court's denial of the application for a temporary restraining order and preliminary injunction, considering the applicability of Presidential Decree No. 1818. Whether the termination of the contract by the DPWH was proper given the negative slippage of 9.86%, considering the stipulations in Presidential Decree No. 1870 and DPWH Department Order No. 102. Whether the delays and negative slippage were attributable to the fault of the government, specifically the DPWH's failure to secure the required right-of-way, and the interpretation of Presidential Decree No. 1870 regarding the DPWH's authority to take over the project. Whether the financial implications of the wrongful termination and rebidding of the project, particularly if awarded to a disqualified bidder, impact the public interest and warrant the issuance of an injunction.

Ruling

The petition is granted. The decision and resolution of the Court of Appeals are set aside. The termination of the contract is declared illegal and unjustified.

Ratio Decidendi

On the applicability of Presidential Decree No. 1818 and the denial of the application for a temporary restraining order and preliminary injunction: The Court held that Presidential Decree No. 1818, which prohibits courts from issuing injunctions in cases involving infrastructure projects, is inapplicable in this instance because the petition's objective was not to stop the implementation of a government project, but rather to compel the public respondents to allow the petitioners to proceed with the project due to an allegedly unjustified contract termination. The Court emphasized that its action would be to instruct the public respondents to allow petitioners to proceed, not to halt the project's progress. On the propriety of contract termination based on negative slippage: The Court ruled that the termination of the contract by the DPWH was improper and illegal. Presidential Decree No. 1870 and DPWH Department Order No. 102 clearly stipulate that the government's authority to terminate a contract due to delays arises only when the contractor incurs a negative slippage of fifteen percent (15%) or more. In this case, the negative slippage at the time of termination was only 9.86%. The Court found that the DPWH violated the law and abused its discretion by terminating the contract based on a slippage rate below the legal threshold. The Court stressed that a contract, being a property right, can only be rescinded strictly in accordance with the governing law. On the attribution of delays to government fault and the interpretation of Presidential Decree No. 1870: The Court found that a significant portion of the negative slippage was attributable to the fault of the government, particularly the DPWH's failure to secure the necessary right-of-way for the spoilbank section of the project. The Court rejected the Solicitor General's interpretation that Paragraph 2 of PD 1870 allows the DPWH to take over a project for any delay, regardless of the slippage percentage, holding that this interpretation would create a contradiction with Paragraph 1, which clearly sets the 15% slippage as the trigger for termination. The Court maintained that Paragraph 2 should be interpreted in conjunction with Paragraph 1. On the financial implications and public interest: The Court highlighted the significant financial loss to the government that would result from the wrongful termination and rebidding of the project, particularly if awarded to Hanil Development Corporation, a disqualified bidder whose bid was substantially higher than the government estimate and the petitioners' bid. The Court emphasized that the intent of PD 1870 is to save money and avoid dislocation of government financial projections, which would be contravened by the termination. The Court concluded that public interest and the preservation of taxpayers' money dictate the issuance of the injunction and prohibition.

Main Doctrine

The prohibition under Presidential Decree No. 1818 against issuing injunctions in cases involving infrastructure projects does not apply when the court's action is not to restrain the implementation of a government project, but rather to compel public respondents to allow petitioners to proceed with the project due to an unjustified termination of their contract. Furthermore, the termination of a contract based on negative slippage is only permissible if the slippage reaches fifteen percent (15%) or more, as mandated by Presidential Decree No. 1870 and its implementing circulars, and such termination cannot be justified by reasons attributable to the government itself.

Access audio review, related cases, codal links, and more.

Open LexMatePH →