Aerospace Chemical Industries, Inc. v. Court of Appeals

G.R. No. 108129 · 1999-09-23 · J. QUISUMBING, J.: · Primary: Commercial; Secondary: Civil
REITERATION

Facts

The Antecedents: Aerospace Chemical Industries, Inc. (Aerospace) purchased 500 metric tons of sulfuric acid from Philippine Phosphate Fertilizer Corporation (Philphos). The contract stipulated payment five days prior to shipment and the buyer's responsibility to secure transport. Aerospace paid P553,280.00 on October 3, 1986. Philphos incurred incremental expenses due to Aerospace's delay in hauling the sulfuric acid. Aerospace chartered M/T Sultan Kayumanggi, which only loaded 70.009 MT from Basay and 157.51 MT from Sangi due to the vessel's tilting and subsequent repairs. The vessel later sank with the loaded sulfuric acid. Aerospace chartered another vessel, M/T Don Victor, and requested additional sulfuric acid, which Philphos could not supply due to pyrite limitation. Aerospace filed a complaint for specific performance and/or damages after Philphos demanded payment for storage and maintenance costs. Procedural History: The Regional Trial Court (RTC) ruled in favor of Aerospace, absolving it from liability due to force majeure and finding Philphos in breach of contract for failing to accommodate the additional order. The Court of Appeals (CA) reversed the RTC decision, finding Aerospace guilty of delay and liable for damages, dismissing Aerospace's complaint and ordering it to pay Philphos' counterclaim. The Petition: Aerospace filed a petition for review, assailing the CA's decision and raising issues regarding breach of contract, award of damages, and the applicability of Article 1504 of the Civil Code.

Issue(s)

Whether the respondent court erred in holding that the petitioner committed a breach of contract. Whether the respondent court erred in awarding damages to the private respondent. Whether expenses for the storage and preservation of the purchased fungible goods should be on the seller's account pursuant to Article 1504 of the Civil Code.

Ruling

The petition is denied. The assailed decision of the Court of Appeals is affirmed with modification, reducing the damages awarded to P272,000.00, to be offset against petitioner's advance payment, with the excess amount of P31,483.37 to be returned to petitioner.

Ratio Decidendi

On the issue of breach of contract: The Supreme Court affirmed the Court of Appeals' finding that Aerospace committed a breach of contract. The Court found that the sinking of the vessel M/T Sultan Kayumanggi was not due to force majeure but due to the vessel's inherent instability and unseaworthiness, as evidenced by survey reports. The Court emphasized that it was Aerospace's obligation as the buyer to charter a seaworthy vessel and that its failure to do so, despite repeated demands, constituted a breach. The Court also rejected Aerospace's claim that Philphos' employee verbally recommended purchasing additional sulfuric acid to utilize the vessel's full capacity, citing the parol evidence rule, as this was not substantiated and could not excuse Aerospace's default. On the issue of awarding damages: The Supreme Court upheld the award of damages to Philphos, finding that Aerospace was guilty of unjustified delay in performing its obligation. Article 1170 of the Civil Code provides that those guilty of delay are liable for damages. The Court found that Philphos made a categorical extrajudicial demand on December 12, 1986, requiring Aerospace to lift the cargo by December 15, 1986, or be charged for consequential damages. Aerospace's failure to comply with this demand justified the finding of delay. The Court clarified that the commencement of delay should be reckoned from December 15, 1986, not August 6, 1986, as the earlier letter was a mere statement of fact regarding potential costs, not a categorical demand. On the issue of storage and maintenance expenses for fungible goods: The Supreme Court ruled that Article 1504 of the Civil Code, which generally places the risk of loss on the seller until ownership is transferred, is not applicable when actual delivery has been delayed through the fault of the buyer. In this case, Aerospace's delay in lifting the sulfuric acid made it liable for the storage and maintenance expenses incurred by Philphos. The Court found that Philphos extended its lease agreement for the Sangi, Cebu storage tank solely for Aerospace's sulfuric acid and that Aerospace should reimburse these expenses from December 15, 1986, to August 31, 1987. The Court also noted that Philphos was not remiss in reminding Aerospace of its liability for these expenses.

Main Doctrine

The buyer incurs delay when it fails to lift the purchased goods within the agreed period, making it liable for damages, including storage and maintenance expenses, even if the goods are fungible, as the risk of loss shifts to the buyer in case of delay due to the buyer's fault.

Access audio review, related cases, codal links, and more.

Open LexMatePH →