Allen v. Province of Albay

G.R. No. 11433 · 1916-12-20 · J. TRENT, J.: · Primary: Civil; Secondary: Contracts, Damages
REITERATION

Facts

The Antecedents: Arthur F. Allen entered into a contract with the Provinces of Albay and Ambos Camarines for the construction of a bridge over the Agus River. The contract, executed on June 26, 1913, stipulated completion on or before September 1, 1913, with a penalty of P25 per day for delay. The plaintiff submitted a bid of P30,690. The bridge was completed and accepted on April 1, 1914. The provinces withheld P1,301.45 from the contract price, representing liquidated damages (P925), inspection expenses (P175.03), and ferry operation costs (P201.42). Allen instituted this action to recover the withheld amount, plus claims for overcharges on steel, damages for delay, and extra work. Procedural History: The Court of First Instance rendered a judgment in favor of the defendants, dismissing the complaint on the merits. The plaintiff appealed this decision. The Petition: The plaintiff appealed, arguing that the trial court erred in finding him responsible for the delay, in holding the defendants entitled to deduct the sums for liquidated damages, ferry operation, and inspection, and in dismissing his complaint.

Issue(s)

Whether the provinces waived the original contract completion date due to their own acts and omissions. Whether the court may apportion the delay between the contractor and the owner to enforce liquidated damages.

Ruling

The Supreme Court reversed the judgment of the lower court. It ruled in favor of the plaintiff, Arthur F. Allen, ordering the defendants to pay him the sum of P1,301.45, with legal interest from April 1, 1914. No costs were awarded.

Ratio Decidendi

On Issue 1: The Court ruled that the provinces waived the strict contract time (whether September 1 or November 1) because they failed to deliver the steel promptly. The final shipment of steel arrived at Legaspi on the very day the contract was supposed to be completed, making it impossible for the contractor to finish on time. Furthermore, the enforcement of a strict quarantine on animals by the authorities and the substantial changes made to the bridge plans after October 12 further prevented adherence to the original schedule. Applying the rule in District of Columbia v. Camden Iron Works, the Court held that where strict performance is prevented or waived by the owner, they cannot sustain a claim for fines or penalties for delay. On Issue 2: The Court explicitly rejected the theory of 'apportioning' delay between the parties. Even if the contractor were responsible for a significant portion of the total delay and the provinces were only responsible for a few days, the liquidated damages clause is considered eliminated once the deadline is waived. The Court cited Jefferson Hotel Co. v. Brumbaugh and Mosler Safe Co. v. Maiden Lane Safe Dep. Co. to emphasize that when parties are mutually responsible for delays, the obligation for liquidated damages is annulled and cannot be revived. Consequently, the provinces were only entitled to actual damages resulting from an unreasonable delay; however, since no actual damages were proven for the period after the requested extension (February 15), the deductions for liquidated damages, inspection, and ferry maintenance were unlawful.

Main Doctrine

Where strict performance on the part of the contractor is prevented or waived by the other party, a claim by such party of fines and penalties for delay or failure cannot be sustained. The waiver operates to eliminate the definite date from which to assess liquidated damages, and while the contractor is obligated to complete the work within a reasonable time, the liquidated damage clause is not thereby restored.

Access audio review, related cases, codal links, and more.

Open LexMatePH →