Mea Builders, Inc. v. Metropolitan Bank and Trust Company

G.R. No. 121484 · 2005-01-31 · J. CORONA, J.: · Primary: Commercial; Secondary: Civil
REITERATION

Facts

The Antecedents: MEA Builders, Inc. (MEA) entered into a construction contract with Capital Resources Corporation (CRC) for housing units. A tripartite agreement was subsequently executed among MEA, CRC, and Metropolitan Bank and Trust Company (Metrobank), wherein Metrobank agreed to issue stand-by letters of credit for the cash portion of payments, subject to conditions including the completion of housing units attested by a Certificate of Completion and an HFC Guarantee. MEA and CRC later amended the contract price. MEA also entered into a separate contract with CRC for horizontal development. MEA obtained an advance of P3,000,000 from Metrobank, covered by a promissory note and suretyship agreements, which was partially liquidated, resulting in a new P1.5 million promissory note. MEA completed 45 single detached units, for which Metrobank paid P3,274,263.22. MEA later suspended operations and demanded payment. Metrobank filed a collection case for the P1.5 million promissory note. Procedural History: The Regional Trial Court (RTC) ruled in favor of MEA on its counterclaim, finding the P1.5 million promissory note to be an advance payment tied to the construction work and not a straight loan. The RTC awarded MEA P18,200,000 for work performed, P9,000,000 for damages, 3% monthly interest, and attorney's fees. The Court of Appeals (CA) modified the RTC decision, reducing the award to P6,308,484.54, less payments and the P1.5 million loan with interest, and deleted the awards for damages and attorney's fees. The CA found that the RTC overcomputed the award and failed to consider deductions and Metrobank's limited liability. The Petition: Petitioners MEA Builders, Inc., Vicente Llave, Ernesto Yu, and Angel Yuanlian assail the CA decision, arguing that it misapprehended evidence, erred in computing the value of work accomplished, in ruling against actual and compensatory damages, in deducting payments already accounted for, and in disallowing attorney's fees. They also argue that Metrobank is entitled to interest and penalty charges on the promissory note.

Issue(s)

Whether the Court of Appeals erred in its computation of the value of work actually accomplished by MEA Builders, Inc. Whether petitioners are entitled to actual and compensatory damages. Whether the Court of Appeals erred in deducting payments already accounted for. Whether petitioners are entitled to attorney's fees. Whether the Court of Appeals erred in ruling that Metrobank is entitled to interest and penalty charges on the promissory note.

Ruling

The petition is denied, and the decision of the Court of Appeals is affirmed in toto. Metrobank's liability is limited to the value of completed housing units as per the tripartite agreement, less payments made and the outstanding loan. Awards for damages and attorney's fees were deleted.

Ratio Decidendi

On the computation of work accomplished: The Supreme Court affirmed the Court of Appeals' reduction of the award. The Court reiterated that Metrobank's obligation was limited to what was stipulated in the tripartite agreement, which was conditioned on the completion of units attested by a Certificate of Completion. The Court found that the appellate court correctly considered that Metrobank had already paid for 45 units amounting to P3,274,263.22, which should be deducted from the value of the 120 units reported as built. Furthermore, the Court agreed that the trial court erred in including the claim for the horizontal project, as Metrobank was not a party to that contract, and in including the cost of filling materials, which was chargeable to CRC, not Metrobank. The Court also noted that only the January 18, 1983 progress report was accepted by CRC, pertaining to 55 vertical units valued at P6,308,484.54, from which the payments and the P1.5 million loan should be deducted. On actual and compensatory damages: The Supreme Court upheld the deletion of the P9,000,000 award for actual and compensatory damages. The Court emphasized that damages require proof with reasonable certainty. Petitioners failed to establish these damages, as the trial court's basis was the testimony of petitioner Llave, who made a sweeping statement about unrealized profits and interest, without tangible documentary proof. The Court also found no breach of contractual obligation or bad faith on Metrobank's part when it suggested suspending construction for mutual protection. On the deduction of payments: The Supreme Court affirmed the Court of Appeals' deduction of P3,274,263.22 for the 45 completed units. The Court found that this amount represented payments made by Metrobank for those specific units and should be deducted from the total value of work accomplished, as per the tripartite agreement's conditions. The argument that this amount was already deducted was not substantiated in a manner that would overturn the appellate court's findings. On attorney's fees: The Supreme Court agreed with the Court of Appeals that the award of attorney's fees was not justified. The Court reiterated that the grant of attorney's fees is an exception to the rule and requires specific findings of fact and law that bring the case within the exceptions provided by law, which were absent in this case. The mere fact of winning a case does not automatically entitle a party to attorney's fees. On interest and penalty charges on the promissory note: The Supreme Court affirmed the Court of Appeals' ruling that Metrobank is entitled to interest and penalty charges on the P1.5 million promissory note. The Court found that the promissory note was a separate obligation from the tripartite agreement, and MEA had defaulted on its payment. Therefore, Metrobank was entitled to recover the principal amount plus the stipulated interest and penalties as provided in the note.

Main Doctrine

Metrobank's liability under the tripartite agreement is limited to the value of completed housing units as attested by certificates of completion, and does not extend to projects for which Metrobank was not a party, nor to costs advanced by the contractor that were chargeable to another entity. Furthermore, claims for actual and compensatory damages require proof with reasonable certainty, and awards of attorney's fees are exceptions that must be justified by specific circumstances.

Access audio review, related cases, codal links, and more.

Open LexMatePH →