Department of Health v. HTMC Engineers Company

G.R. No. 146120 · 2006-01-27 · J. CHICO-NAZARIO, J.: · Primary: Commercial; Secondary: Civil
REITERATION

Facts

1. The Antecedents: The Department of Health (DOH) entered into four Owner-Consultant Agreements with HTMC Engineers Company (HTMC) for various infrastructure projects at four medical centers. These agreements stipulated that HTMC would provide architectural and engineering (A&E) design plans, bid documents, and construction supervision (CS), with a professional fee of 7.5% of the project fund allocation. HTMC completed the A&E services and submitted the required documents. However, the DOH proposed amendments to the agreements, including dividing the scope of work and altering the fee structure and basis of payment. HTMC responded with a position paper outlining its terms, but no clear settlement was reached, leading to the DOH's refusal to issue notices to proceed for construction supervision. This refusal, coupled with the DOH's insistence on a different payment basis, prompted HTMC to demand the balance of its consultancy fees and fees for other works, threatening arbitration if the demands were not met. 2. Procedural History: Following the DOH's continued refusal to settle the dispute and issue notices to proceed, HTMC filed a claim for arbitration with the Construction Industry Arbitration Commission (CIAC). Arbitrator Custodio Parlade issued a decision in favor of HTMC, awarding a total of P4,430,174.00 with interest. The DOH then filed a petition for review with the Court of Appeals, challenging the CIAC's jurisdiction and the monetary award. The Court of Appeals denied the petition, affirming the CIAC's decision and dismissing the DOH's arguments regarding jurisdiction and the award. The DOH's subsequent motion for reconsideration was also denied, leading to the present petition. 3. The Petition: This case comes before the Supreme Court via a Petition for Review on Certiorari under Rule 45 of the Rules of Civil Procedure. The petitioner, the Department of Health, raises two main issues: first, whether the Court of Appeals erred in affirming the CIAC's jurisdiction over the claim, and second, whether the Court of Appeals erred in upholding the monetary award made by the CIAC arbitrator as being in accordance with the consultancy agreements. The DOH argues that the CIAC lacked jurisdiction and that the award was improperly calculated. The petition seeks to overturn the decision of the Court of Appeals and, consequently, the award made by the CIAC.

Issue(s)

Whether the Construction Industry Arbitration Commission (CIAC) had jurisdiction over the claim. Whether the monetary award by the CIAC arbitrator was in accord with the tenor of the consultancy agreements.

Ruling

The Supreme Court denied the petition for review on certiorari, affirming the decision of the Court of Appeals which upheld the ruling of the Construction Industry Arbitration Commission (CIAC). The Court ruled that the CIAC had jurisdiction over the dispute and that the monetary award was in accordance with the consultancy agreements.

Ratio Decidendi

On the issue of CIAC's jurisdiction: The Supreme Court affirmed that the CIAC has original and exclusive jurisdiction over disputes arising from construction contracts, as provided by Section 4 of Executive Order No. 1008. Article 12 of the consultancy agreements explicitly provided for arbitration. Even though the agreement initially designated the Secretary of Health to decide disputes, it also stipulated that the decision would be final and conclusive unless the consultant desired arbitration within thirty days, in which case the dispute would be decided in accordance with the CIAC Rules under E.O. 1008. The Court found that HTMC properly submitted its claim to the CIAC after the DOH failed to act on its requests and demand letter, making the referral to CIAC not premature. The Court reiterated that an arbitration clause in a construction contract, even if referring to a different institution, is deemed an agreement to submit to CIAC jurisdiction if the parties agree to voluntary arbitration under E.O. 1008. The DOH's refusal to issue notices to proceed and its insistence on amending the contract did not divest CIAC of its jurisdiction. On the issue of the monetary award: The Supreme Court found the monetary award to be in accord with the tenor of the consultancy agreements, which constitute the law between the parties. The Court emphasized that HTMC's failure to accept the DOH's proposed amendments did not affect the validity and subsistence of the original contracts. Since no new contract was perfected, the terms of the original contract continued to govern. The DOH was therefore obligated to pay HTMC the unpaid sum of its consultancy fees, which the CIAC found to be P3,543,630.00 for A&E services. Furthermore, the Court upheld the award of damages for unrealized profit (P310,544.00) and reimbursement for expenses (P576,000.00) due to the DOH's refusal to issue the notices to proceed, which prevented HTMC from performing its construction supervision obligations. This refusal constituted a breach of the contract, making the DOH liable for damages naturally resulting from such breach. The Court also noted that the issue of the alleged failure to include a certification of availability of funds was raised for the first time on appeal and thus could not be considered.

Main Doctrine

The Construction Industry Arbitration Commission (CIAC) has original and exclusive jurisdiction over disputes arising from construction contracts, even if the contract contains an arbitration clause referring to a different body, as long as the parties agree to submit the dispute to voluntary arbitration under Executive Order No. 1008. A perfected contract remains valid and binding despite a party's refusal to accede to proposed amendments, and the non-performance of contractual obligations due to the other party's breach entitles the injured party to damages.

Access audio review, related cases, codal links, and more.

Open LexMatePH →