Smith, Bell & Co. v. Sotelo

G.R. No. 16570 · 1922-03-09 · J. ROMUALDEZ, J.: · Primary: Commercial; Secondary: Civil
REITERATION

Facts

The Antecedents: Plaintiff corporation and defendant entered into contracts for the sale of two steel tanks, two expellers, and two electric motors. The tanks were to be delivered within three to four months, the expellers in September 1918 or as soon as possible, and the motors within ninety days, with the latter's delivery not guaranteed. The tanks arrived in April 1919, the expellers in October 1918, and the motors in February 1919. The plaintiff notified the defendant of the arrival, but the defendant refused to receive the goods and pay the stipulated prices. Procedural History: The plaintiff filed suit based on four causes of action. The defendant and intervenor denied the plaintiff's allegations, asserting that the goods arrived incomplete and long after the stipulated dates, and that the defendant acted as manager for the intervenor. They counterclaimed for damages due to the plaintiff's delay. The trial court absolved the defendants regarding the tanks and motors but ordered them to accept the expellers and pay P50,000. Both parties appealed. The Petition: Both parties appealed the trial court's decision, assigning errors to the findings. The principal issue was whether the plaintiff fulfilled its obligation to deliver the goods in Manila within the agreed-upon time.

Issue(s)

Whether the plaintiff fulfilled its obligation to deliver the goods within the stipulated or a reasonable time. Whether the defendant, acting as an agent, can shield himself behind the intervenor, or if the intervenor has a right of action against the plaintiff. Whether the plaintiff is entitled to the relief prayed for in its complaint.

Ruling

The Supreme Court modified the judgment, ordering the defendant, Mr. Vicente Sotelo Matti, to accept and receive the tanks, expellers, and motors, and to pay the plaintiff the sum of P96,000, with legal interest from July 17, 1919, and costs.

Ratio Decidendi

On the issue of delivery time and fulfillment of obligation: The Court held that the contracts did not fix a definite date for delivery, as the stipulated periods were qualified by contingencies such as government regulations, railroad embargoes, lack of vessel space, and the exigencies of the United States Government's requirements. These clauses indicated that the delivery was subject to conditions beyond the seller's control, making the obligations conditional. Citing Article 1125 of the Civil Code, the Court noted that if the uncertainty consists in the arrival or non-arrival of a day, the obligation is conditional. However, in cases where the fulfillment of the condition depends on the will of a third person who cannot be compelled to fulfill it, and the obligor has done all in their power to comply, the obligor is deemed to have sufficiently performed their part. The Court found sufficient proof that the plaintiff made all possible efforts to bring the goods to Manila as soon as possible, and upon arrival, immediately notified the defendant. Therefore, the machinery was brought to Manila within a reasonable time, and the plaintiff was not guilty of delay. The Court also referenced North American jurisprudence, which regards time as unessential when not fixed in a contract, requiring delivery within a reasonable time. The circumstances, including the world war and its impact on shipping and export restrictions, supported the conclusion that the plaintiff acted with reasonable diligence. On the issue of agency and right of action: The Court clarified that the contracts were signed by the defendant, Mr. Vicente Sotelo, in his individual capacity and own name. If he was acting as an agent for the intervenor, the intervenor had no right of action against the plaintiff based on Article 1717 of the Civil Code and Article 246 of the Code of Commerce. These provisions state that when an agent acts in his own name, he is directly liable as if the transaction were his own, and the principal has no right of action against the third party, nor vice versa, except for actions between the principal and agent. Since the contracts were not made in the name of the principal, the intervenor could not claim damages arising from the plaintiff's alleged delay. On the plaintiff's entitlement to relief: Based on the findings that the plaintiff fulfilled its obligation by delivering the goods within a reasonable time despite unforeseen circumstances and that the intervenor had no right of action due to the agent transacting in his own name, the Court concluded that the plaintiff was entitled to the relief prayed for in its complaint. The damages alleged by the intervenor were not imputable to the plaintiff. Consequently, the judgment of the lower court was modified to grant the plaintiff the full amount sought.

Main Doctrine

Where the delivery of goods in a contract of sale is subject to contingencies beyond the seller's control, and the seller has exerted all possible efforts to fulfill the obligation, the delivery is considered made within a reasonable time, and the seller is not guilty of delay. Furthermore, when an agent transacts business in his own name, he is directly liable, and the principal has no right of action against the third party.

Access audio review, related cases, codal links, and more.

Open LexMatePH →