Campbell & Go-Tauco v. Behn, Meyer & Co.

G.R. No. 1490 · 1904-04-02 · J. MCDONOUGH, J.: · Primary: Commercial; Secondary: Civil
REITERATION

Facts

The Antecedents: Plaintiffs O. F. Campbell & Go-Tauco entered into two contracts with defendants Behn, Meyer & Co. The first contract, dated July 20, 1901, was for the construction of a dwelling for P15,000, payable in installments, with a three-month completion period. The second contract, dated June 20, 1901, was for filling a lot on the Pasig River bank with earth and sand at P1.30 per cubic meter, with an estimated delivery of over 15,000 cubic meters monthly. During the construction of the house, alterations and extra work were made, increasing the total cost to P22,750.62. Plaintiffs claimed an unpaid balance of P9,250.62. Defendants disputed liability for P2,333.12 of this amount, alleging unworkmanlike construction. Defendants also counterclaimed for P71,197.65, alleging that plaintiffs misrepresented the amount of sand and earth used for filling the lot, and that they paid for 31,690.50 cubic meters that were not used. Procedural History: The Court of First Instance dismissed the plaintiffs' complaint and ordered the defendants to recover P52,000 from the plaintiffs, based on the court's finding that defendants paid for sand and dirt not placed on the lot. The court also denied the plaintiffs any compensation beyond what they had already received due to alleged defective construction. The Petition: Plaintiffs appealed the decision of the Court of First Instance.

Issue(s)

Whether the plaintiffs are entitled to the unpaid balance for the construction of the dwelling. Whether the defendants are entitled to recover the sum of P52,000 for alleged undelivered sand and earth. Whether the plaintiffs are entitled to payment for additional sand and earth claimed in their reply.

Ruling

The Supreme Court reversed the decision of the Court of First Instance. It ruled that the plaintiffs are entitled to recover the unpaid balance of P9,250.62 for the construction of the dwelling. The Court also ruled that the defendants are not entitled to recover the P52,000 claimed for undelivered sand and earth, and disallowed the plaintiffs' claim for additional payment for sand and earth.

Ratio Decidendi

On the unpaid balance for the dwelling construction: The Court found that the plaintiffs substantially complied with the contract, plans, and specifications for the dwelling. The defendants accepted the house by occupying it, which constitutes an acknowledgment of substantial performance. Any defects noted were either due to the quality of materials specified by the defendants, the plans and specifications themselves, or the directions of the defendants' inspecting engineer, whose instructions the plaintiffs followed. Therefore, the plaintiffs are entitled to the unpaid balance of P9,250.62. On the defendants' counterclaim for undelivered sand and earth: The Court held that the defendants failed to prove their claim that they did not receive the full amount of sand and earth for which they paid. The evidence showed that the sand was measured by the defendants' own agents at the time of delivery, and receipts and payments were made based on these measurements. The defendants' subsequent expert measurements, taken long after delivery and with potential inaccuracies due to the nature of the lot and settlement, were not sufficient to disprove their own contemporaneous measurements and records. The Court applied the doctrine of estoppel, stating that the defendants, having measured, receipted for, and paid for the sand, could not later deny its receipt in the absence of proof of fraud or deceit. On the plaintiffs' claim for additional payment for sand and earth: The Court disallowed the plaintiffs' claim for P2,279.55 for additional sand and earth, finding that they had not satisfactorily proven the delivery of this extra amount.

Main Doctrine

Where a building contract is substantially performed and the owner accepts the building by occupying it, the contractor is entitled to recover the unpaid balance, and the owner cannot claim damages for defects that are attributable to the plans, specifications, or the directions of the owner's engineer, or to the quality of materials specified by the owner. Furthermore, a party who has measured, receipted for, and paid for materials cannot later claim recovery based on a mutual mistake of fact in the absence of fraud or deceit.

Access audio review, related cases, codal links, and more.

Open LexMatePH →