Federal Builders v. Daiichi Properties

G.R. No. 142525 · 2009-02-13 · J. CHICO-NAZARIO, J.: · Primary: Commercial; Secondary: Remedial
REITERATION

Facts

The Antecedents: Federal Builders, Inc. (Federal) was the winning bidder for the general construction of Daiichi Properties and Development, Inc.'s (Daiichi) high-rise building project, Orient Plaza. The Construction Agreement stipulated that Daiichi would provide cement and steel bars, while Federal would supply labor and other materials, with a fixed price for Federal's contribution. The agreement also allowed Daiichi to revise construction plans, obligating Federal to undertake additional or omitted work. Procedural History: During construction, Daiichi reduced the concrete strength, leading to revised plans and a decrease in required materials and labor costs. The parties disagreed on the method for calculating the deductive costs arising from these revisions. Daiichi proposed a method based on the difference between original and revised plan quantities, while Federal used a formula comparing guaranteed maximum quantities with revised plan quantities. Daiichi engaged an independent quantity surveyor, DLS, whose estimate was closer to Daiichi's computation. Federal filed a petition for arbitration with the Construction Industry Arbitration Commission (CIAC). Daiichi filed a Motion to Commission an Independent Quantity Surveyor to determine actual material quantities under both plans, which the Arbitral Tribunal denied. The Court of Appeals set aside the Arbitral Tribunal's orders, directing it to commission an independent quantity surveyor. Federal's motion for reconsideration was denied, leading to the present petition. The Petition: Federal Builders, Inc. filed a Petition for Review on Certiorari under Rule 65, assailing the Court of Appeals' Decision and Resolution that nullified the Arbitral Tribunal's orders and directed the commissioning of an independent quantity surveyor.

Issue(s)

Whether the Court of Appeals erred in granting Daiichi's petition and ordering the Arbitral Tribunal to commission an independent quantity surveyor; and whether the Court of Appeals encroached on the Arbitral Tribunal's jurisdiction. Whether the Arbitral Tribunal committed grave abuse of discretion in denying Daiichi's motion to commission an independent quantity surveyor; and the procedural defect of filing a Rule 65 petition instead of a Rule 45 petition.

Ruling

The Supreme Court affirmed the Decision of the Court of Appeals, holding that the Arbitral Tribunal committed grave abuse of discretion amounting to lack of jurisdiction in denying Daiichi's motion to commission an independent quantity surveyor. The Court directed the Arbitral Tribunal to issue an order commissioning an independent surveyor to determine the actual quantities of materials required under the original and revised plans, and thereafter, to resolve the main case.

Ratio Decidendi

On the issue of the Court of Appeals' decision to grant Daiichi's petition and order the commissioning of an independent quantity surveyor, and whether the Court of Appeals encroached on the Arbitral Tribunal's jurisdiction: The Court clarified that the Court of Appeals primarily resolved the issue of grave abuse of discretion by the Arbitral Tribunal. While the appellate court may have intimated that Daiichi's formula was desirable, this was to emphasize that the Arbitral Tribunal could not, without abusing its discretion, preclude Daiichi from presenting evidence. The Court of Appeals did not pre-empt the Arbitral Tribunal's decision on the main case, as evidenced by its statement that the worth of a second survey report would be for the Tribunal to decide. The dispositive portion of the Court of Appeals' decision only directed the commissioning of an independent surveyor, not the adoption of Daiichi's formula. On the issue of grave abuse of discretion and the denial of the motion to commission an independent quantity surveyor, and the procedural defect: The Supreme Court held that the Court of Appeals did not commit grave abuse of discretion in reversing the Arbitral Tribunal's orders. The crux of the controversy was the determination of deductive costs, which required comparing material quantities under the original and revised plans. The Arbitral Tribunal's refusal to allow Daiichi to commission an independent survey on these unknown items effectively prevented Daiichi from presenting evidence to substantiate its theory. The Court emphasized that arbitration proceedings, like judicial ones, require arbitrators to use all reasonable means to ascertain facts objectively. The denial of the motion, which was a reasonable attempt to provide the tribunal with credible information to resolve the dispute, was deemed capricious and arbitrary, amounting to grave abuse of discretion. The tribunal's justification that an independent surveyor is only useful if both parties agree was found to be specious, as the Rules of Procedure Governing Construction Arbitration allow for the appointment of experts upon the request of one party. The Court noted that Federal chose the wrong remedy by filing a petition for certiorari under Rule 65 instead of a petition for review under Rule 45. However, the Court chose to ignore this procedural defect and proceeded to rule on the merits of the case, stating that even if the procedural defects were considered, the petition would still be dismissed because the Court of Appeals did not commit grave abuse of discretion. This indicates the Court's preference for substantial justice over strict adherence to procedural technicalities when the merits of the case are clear.

Main Doctrine

The Arbitral Tribunal committed grave abuse of discretion amounting to lack of jurisdiction when it denied the motion to commission an independent quantity surveyor, as such action prevented a party from presenting vital evidence necessary for the judicious resolution of the dispute, contrary to the mandate of the Rules of Procedure Governing Construction Arbitration to use all reasonable means to ascertain facts.

Access audio review, related cases, codal links, and more.

Open LexMatePH →