Urban Consolidated Constructors v. Insular Life Assurance

G.R. No. 180824 · 2009-08-28 · J. YNARES-SANTIAGO, J.: · Primary: Commercial; Secondary: Civil
REITERATION

Facts

The Antecedents: Respondent Insular Life Assurance Co., Inc. (Insular) engaged petitioner Urban Consolidated Constructors Philippines, Inc. (Urban) to construct a six-storey building. The original contract was for 365 days at P30,498,689.00. The parties later executed a General Construction Agreement (GCA) extending the deadline to June 30, 1991, and increasing the contract price to P38,885,000.00. The deadline was further moved to September 30, 1991. Urban experienced several delays and tendered the building for acceptance on July 21, 1992, which Insular refused. Procedural History: Urban filed a collection case against Insular, claiming Insular caused the delay through various actions and omissions, and seeking damages. Insular counterclaimed for liquidated damages. The Regional Trial Court (RTC) ruled in favor of Urban, ordering Insular to pay actual damages. Insular appealed to the Court of Appeals (CA), which reversed the RTC decision, finding Insular entitled to liquidated damages but reducing the amount. The CA ordered Insular to pay Urban certain amounts for change orders and retention money, while Urban was ordered to pay Insular liquidated damages. Both parties filed motions for reconsideration, which were denied. The Petition: Urban filed a petition for review on certiorari, contending it should not be liable for liquidated damages because the delay was caused by Insular's requests for change orders and failure to procure major construction materials. The Supreme Court was tasked to resolve whether Urban is liable for liquidated damages.

Issue(s)

Whether petitioner Urban Consolidated Constructors Philippines, Inc. is liable to pay liquidated damages to respondent Insular Life Assurance Co., Inc., and whether the delay in the completion of the construction project was caused by Insular or Urban. Whether the liquidated damages awarded by the Court of Appeals should be equitably reduced.

Ruling

The Supreme Court affirmed the Court of Appeals' decision with modification, holding Urban liable for liquidated damages but reducing the amount. The Court ruled that Urban is liable for liquidated damages, but the amount was further reduced from P2,940,000.00 to P1,940,000.00.

Ratio Decidendi

On the liability for liquidated damages and cause of delay: The Court sustained the Court of Appeals' finding that Urban is liable for liquidated damages. The GCA explicitly stated that the contractor (Urban) shall furnish and supply all necessary materials, labor, equipment, and tools. While Insular agreed to purchase major construction materials in advance and pay suppliers directly as financial assistance, this was never reflected as an obligation to procure and deliver the materials. Urban's president himself acknowledged this as financial assistance. Therefore, the delay in construction cannot be attributed to Insular's alleged failure to procure materials. The Court also noted that the delays caused by change orders were considered when the parties extended the completion deadline, and Urban's own lack of funds and failure to facilitate material delivery were significant factors in the delay. The Court reiterated that Urban, as the contractor, had the primary obligation to furnish materials and ensure timely delivery to the construction site. On the equitable reduction of liquidated damages: The Court affirmed the principle that liquidated damages may be equitably reduced when the principal obligation has been partly performed or when the penalty is iniquitous or unconscionable, as provided by Article 1229 of the Civil Code. The Court found that the project was substantially completed (97%) at the time of turnover. Furthermore, Insular was not entirely blameless, as it failed to pay Urban P1,144,030.94 for unpaid change orders and P2,134,908.80 in retention money, totaling P3,578,939.74. Had Insular released these amounts, Urban could have used them to purchase materials and expedite completion. Considering these factors, the Court found it justifiable to further reduce the liquidated damages from P2,940,000.00 to P1,940,000.00, deeming the original amount unconscionable under the circumstances.

Main Doctrine

A contractor is liable for liquidated damages for delay in construction, but the penalty may be equitably reduced by the courts if it is iniquitous or unconscionable, especially when the principal obligation has been partly performed and the other party is also not entirely blameless.

Access audio review, related cases, codal links, and more.

Open LexMatePH →