Adrian Wilson International Associates, Inc. v. TMX Philippines, Inc.

G.R. No. 162608 · 2010-07-26 · J. DEL CASTILLO, J.: · Primary: Civil; Secondary: Commercial
REITERATION

Facts

The Antecedents: TMX Philippines, Inc. (TMX) engaged Adrian Wilson International Associates, Inc. (AWIA) for architectural and engineering services for its watch assembly plant. AWIA's duties included construction administration, specifically guarding TMX against defects and deficiencies by determining the progress and quality of the general contractor's work. Five years after completion, TMX discovered cracks and beam deflections in the roof girders and beams. AWIA initially maintained its design was correct and attributed the issue to marginal concrete strength due to heavy rainfall during pouring, citing a report from its site representative, Engr. Gavino Lacanilao. However, other consultancy firms, Fletcher-Thompson and C.N. Ramientos and Associates, concluded the defects were due to AWIA's design errors. TMX, as a preventive and corrective measure, installed 118 steel lally columns, incurring expenses of ₱2,385,499.00 for shoring and ₱1,546,084.00 for employee salaries during a work stoppage from December 1-18, 1985. TMX sued AWIA for reimbursement. Procedural History: The Regional Trial Court (RTC) ordered AWIA to pay TMX ₱222,377.00 for 11 shoring columns (reduced from 118) and ₱80,000.00 for attorney's fees, dismissing claims for salaries. The Court of Appeals (CA) affirmed AWIA's liability for 11 shoring columns but modified the RTC decision by ordering AWIA to reimburse TMX the full amount of ₱1,546,084.00 for employee salaries, finding AWIA failed to adequately notify TMX of defects. The Petition: AWIA filed a petition for review on certiorari with the Supreme Court, assailing the CA's decision regarding its liability for construction administration and the reimbursement of employee salaries.

Issue(s)

Whether AWIA properly discharged its duty as construction administrator. Whether there is a valid basis for the reimbursement of the salaries paid to TMX employees during the work stoppage.

Ruling

The Supreme Court partially granted the petition. It affirmed the finding that AWIA breached its duty of contract administration, leading to TMX's expenses. However, it modified the CA's award for salaries, deleting the ₱1,546,084.00 actual damages and awarding ₱500,000.00 as temperate damages in lieu thereof.

Ratio Decidendi

On the issue of AWIA's duty as construction administrator: The Court held that AWIA failed in its duty to guard TMX against the contractor's work deficiencies. The Agreement explicitly tasked AWIA with making periodic visits to determine the progress and quality of work, and to promptly notify the owner in writing of defects and deficiencies, and determine how they would be rectified. AWIA's report on the July 18, 1979 incident, which merely narrated events and Engr. Lacanilao's actions, did not adequately warn TMX of potential jeopardy to the roof's structural integrity. AWIA's subsequent approval of progress billings and issuance of a final certification of payment, despite the potential issue with concrete strength, was a breach of its obligation. The Court found a causal connection between AWIA's negligence in informing TMX and the expenses TMX incurred for repairs, including the plant shutdown and employee salaries. The ruling that AWIA was liable for the cost of 11 shoring columns was no longer challenged by AWIA, thus becoming final and executory. On the issue of reimbursement for employee salaries: The Court found that TMX failed to substantiate its claim for the full reimbursement of ₱1,546,084.00 as actual damages. The evidence presented, consisting of master lists, summarized payroll costs, salary structures, and check vouchers, did not show actual payment and receipt by employees but merely reflected disbursement records. Vouchers are not receipts, and the RTC correctly preferred payroll documents with employee signatures as the best evidence of payment. However, acknowledging that TMX did incur pecuniary loss due to the shutdown and the structural problem, and considering that the installation of fewer columns would have shortened the repair period, the Court awarded temperate damages of ₱500,000.00 as a matter of equity. This amount was deemed reasonable and sufficient under the circumstances, recognizing TMX's proven loss but also the lack of exact proof for the claimed actual damages.

Main Doctrine

An architect or engineering consultant engaged for construction administration has a duty to promptly and adequately inform the owner in writing of any defects and deficiencies in the work of the contractor and determine how such problems could be rectified. Failure to do so constitutes a breach of contract, making the consultant liable for damages naturally and probably resulting from the breach. While actual damages must be proven with certainty, temperate damages may be awarded when pecuniary loss has been suffered but the exact amount cannot be determined.

Access audio review, related cases, codal links, and more.

Open LexMatePH →