Golangco Construction Corp. v. Ray Burton Development Corp.

G.R. No. 163582 · 2010-08-09 · J. PERALTA, J.: · Primary: Commercial; Secondary: Remedial
REITERATION

Facts

1. The Antecedents: Ray Burton Development Corporation (RBDC) and William Golangco Construction Corporation (WGCC) entered into a contract for the construction of the Elizabeth Place condominium. Subsequently, WGCC filed a complaint with the Construction Industry Arbitration Commission (CIAC) seeking payment for various outstanding balances and charges totaling P53,667,219.45, plus interest, related to the construction contract. 2. Procedural History: RBDC moved to dismiss WGCC's complaint before the CIAC, arguing that the CIAC lacked jurisdiction because the arbitration clause in their contract only covered disputes arising from differences in contract interpretation, not collection of sums of money. The CIAC denied this motion, asserting its jurisdiction. RBDC then filed a petition for certiorari and prohibition with the Court of Appeals (CA), again challenging the CIAC's jurisdiction. The CA granted RBDC's petition, ruling that the CIAC did not have jurisdiction. WGCC moved for reconsideration, which was denied, leading to the present petition before the Supreme Court. 3. The Petition: WGCC filed a Petition for Review on Certiorari under Rule 45 of the Rules of Court, assailing the CA's decision and resolution. WGCC argues that the CA erred in not dismissing RBDC's petition for certiorari for failing to attach relevant pleadings and for not filing a motion for reconsideration of the CIAC's order. Furthermore, WGCC contends that the CA erred in ruling that the CIAC lacked jurisdiction, asserting that the dispute indeed involved contract interpretation and that the CIAC's jurisdiction is established by law (Executive Order No. 1008) and the arbitration clause in the contract, regardless of specific wording.

Issue(s)

Whether the Court of Appeals acted with grave abuse of discretion in failing to dismiss respondent RBDC's petition for certiorari due to non-compliance with formal requirements. Whether the Court of Appeals erred in ruling that the CIAC had no jurisdiction over WGCC's claims.

Ruling

The Supreme Court granted the petition, reversed and set aside the decision and resolution of the Court of Appeals, and reinstated the order of the Construction Industry Arbitration Commission.

Ratio Decidendi

On the procedural issue of the CA's failure to dismiss the petition for certiorari: The Supreme Court held that the Court of Appeals erred in giving due course to the petition for certiorari filed by RBDC. Petitioner WGCC correctly argued that RBDC failed to comply with the mandatory requirements under Rule 65, Section 1, in relation to Section 3, Rule 46 of the Revised Rules of Court. Specifically, RBDC failed to attach copies of relevant pleadings from the CIAC case, such as the Complaint, Motion to Dismiss, Comment and Opposition, and Motion to Suspend Proceedings. The Court emphasized that the failure to comply with these requirements is a sufficient ground for the dismissal of the petition. The CA's order to submit the missing documents did not cure the initial defect, and there was no convincing reason to relax the rules in favor of RBDC. Therefore, the CA acted with grave abuse of discretion in not dismissing the petition outright on these procedural grounds. On the substantive issue of CIAC's jurisdiction: The Supreme Court found that the Court of Appeals gravely erred in ruling that the CIAC had no jurisdiction over the complaint. Section 4 of Executive Order No. 1008 clearly vests the CIAC with original and exclusive jurisdiction over disputes arising from, or connected with, construction contracts, provided the parties agree to submit the same to voluntary arbitration. The arbitration clause in the contract between WGCC and RBDC, particularly Clause 17.2, stated that "any dispute" not resolved by the Board of Arbitrators shall be submitted to the "Construction Arbitration Authority created by the government," which is the CIAC. The Court clarified that the existence of an arbitration clause in a construction contract is, by operation of law, an agreement to submit existing or future controversies to CIAC jurisdiction. This jurisdiction is conferred by law and cannot be diminished or waived by the parties' stipulations. The claims made by WGCC, involving payment for various items under the contract, inherently require the interpretation of the contract provisions to ascertain the parties' duties and obligations, thus constituting a "dispute arising from differences in interpretation of the contract." Even if the dispute did not strictly involve interpretation, the law and the CIAC Rules (Section 1, Article III of the CIAC Rules) provide that an arbitration clause is deemed an agreement to submit to CIAC jurisdiction, notwithstanding reference to a different institution. Therefore, the CIAC properly took cognizance of the complaint.

Main Doctrine

The existence of an arbitration clause in a construction contract is sufficient to vest the Construction Industry Arbitration Commission (CIAC) with jurisdiction over any construction controversy or claim between the parties, regardless of whether the parties specifically choose another forum or make reference to another arbitral body. The CIAC's jurisdiction, conferred by law, cannot be subjected to any condition, nor can it be waived or diminished by the stipulation, act, or omission of the parties.

Access audio review, related cases, codal links, and more.

Open LexMatePH →