Transcept Construction v. Aguilar

G.R. No. 177556 · 2010-12-08 · J. CARPIO, J.: · Primary: Commercial; Secondary: Civil
REITERATION

Facts

The Antecedents: Teresa C. Aguilar (Aguilar) entered into an Owner-General Contractor Agreement (First Contract) with Transcept Construction and Management Professionals, Inc. (Transcept) for a vacation house. Aguilar paid a downpayment. Transcept submitted billings, and Aguilar questioned a second billing, leading Transcept to halt work. Aguilar hired ASTEC, which found substandard work and recommended partial demolition. Transcept and Aguilar then entered into a second agreement (Second Contract) to extend completion and utilize the downpayment. Transcept failed to finish by the new deadline, citing additional works. Aguilar demanded a refund and damages, which Transcept ignored, prompting Aguilar to file a complaint before the Construction Industry Arbitration Commission (CIAC). Procedural History: The CIAC assessed the work accomplished and found substantial completion (98.16%), thus denying liquidated damages but awarding consultancy expenses to Aguilar and additional works cost to Transcept. Aguilar appealed to the Court of Appeals (CA), which reversed the CIAC, finding Transcept only accomplished 87.81% and awarding Aguilar unaccomplished works, consultancy services, and liquidated damages, while deleting the award for additional works. Transcept's motion for reconsideration was denied. The Petition: Transcept filed a petition for review before the Supreme Court, assailing the CA's decision on the entitlement to unaccomplished works, award of liquidated damages, deletion of award for additional works, and award for consultancy services.

Issue(s)

Whether the Court of Appeals erred in holding that Aguilar is entitled to ₱198,916.02 instead of ₱30,076.72 for unaccomplished works. Whether the Court of Appeals erred in awarding Aguilar liquidated damages. Whether the Court of Appeals erred in deleting the CIAC’s award of ₱189,909.91 to Transcept representing additional works done under the Second Contract. Whether the Court of Appeals erred in awarding Aguilar the amount of ₱135,000 for consultancy services.

Ruling

The Supreme Court affirmed the Court of Appeals' Decision and Resolution with modification. It reduced the award for unaccomplished works to ₱30,076.72 and deleted the award for liquidated damages. The Court upheld the deletion of the award for additional works and affirmed the award for consultancy services.

Ratio Decidendi

On the issue of unaccomplished works: The Court found that the Court of Appeals erred in failing to consider that Aguilar presented no evidence on indirect costs for General Requirements and did not cross-examine Transcept's witnesses on this matter. The Court reverted to the CIAC's computation, which included indirect costs as part of the total accomplishment, resulting in a finding of substantial completion. Therefore, the award for unaccomplished works was reduced to ₱30,076.72, representing the difference between the contract price and the CIAC's computed total accomplishment. On the issue of liquidated damages: The Court reiterated that substantial completion, defined as 95% completion of the work, precludes the award of liquidated damages. Based on the CIAC's computation of 98.16% accomplishment, which exceeded the 95% threshold, the Project was considered substantially completed. Consequently, Aguilar was not entitled to liquidated damages, and the award by the Court of Appeals was deleted. On the issue of additional works: The Court agreed with the Court of Appeals that the works performed by Transcept, such as the balcony, lifting of roof beams, and extra fast walls, were not additional works but rather rectifications of substandard work done under the First Contract. The Second Contract was entered into precisely to correct these deficiencies, and Aguilar should not be made to pay for works that were merely corrective measures. On the issue of consultancy services: The Court affirmed the Court of Appeals' award of ₱135,000 for consultancy services. It was established that Aguilar hired ASTEC, a testing laboratory represented by Engr. Rioflorido, to assess Transcept's work. The Court of Appeals correctly found that Aguilar paid Engr. Rioflorido ₱65,000, which, when added to the ₱75,000 awarded by the CIAC, totaled ₱135,000.

Main Doctrine

Substantial completion, defined as completing 95% of the work, precludes the award of liquidated damages, entitling the owner only to actual damages for unaccomplished works. Works done to correct substandard performance under a previous contract, even if not explicitly in the scope of a subsequent contract, are not considered additional works warranting extra payment.

Access audio review, related cases, codal links, and more.

Open LexMatePH →