Licomcen v. Foundation Specialists

G.R. No. 167022 & G.R. No. 169678 · 2011-04-04 · J. ARTURO D. BRION, J.: · Primary: Commercial; Secondary: Remedial
REITERATION

Facts

The Antecedents: LICOMCEN Incorporated (LICOMCEN) entered into a lease contract with the City Government of Legaspi for a lot to construct the LCC Citimall and hired E.S. de Castro and Associates (ESCA) as engineering consultant and Foundation Specialists, Inc. (FSI) for the construction of bored piles foundation. FSI commenced work after signing agreements on September 1, 1997, with a 90-day deadline. On December 16, 1997, LICOMCEN considered major design revisions and suspension of work. ESCA, on January 6, 1998, informed FSI of revised designs necessitating a reduction in bored piles and suggested delivering only 50% of steel bars. On January 15, 1998, LICOMCEN instructed FSI to hold all construction activities due to a pending administrative case before the Ombudsman, with ESCA formalizing the suspension and ordering demobilization on January 19, 1998. FSI demanded payment for costs incurred due to the suspension, totaling ₱22,667,026.97. ESCA objected to some claims, particularly for steel bars delivered in disregard of instructions, which FSI rejected. On March 14, 2001, FSI sent a final demand for ₱29,232,672.83. As LICOMCEN took no action, FSI filed a petition for arbitration with the Construction Industry Arbitration Commission (CIAC) on October 2, 2002, claiming unpaid billings, material costs, equipment and labor standby costs, unrealized gross profit, attorney's fees, and interest. LICOMCEN denied liability, citing the cases filed against it as justification for the suspension and assailing the CIAC's jurisdiction, arguing FSI's claims were not subject to arbitration under GC-61 of the GCC but should be filed in regular courts per GC-05. Procedural History: The CIAC denied LICOMCEN's motion to dismiss for lack of jurisdiction, and the arbitration proceedings continued. On July 7, 2003, the CIAC ruled in favor of FSI, awarding specific amounts for unpaid billings, material costs, equipment and labor standby costs, and unrealized gross profit, and ordered LICOMCEN to bear arbitration costs. LICOMCEN appealed to the Court of Appeals (CA), which upheld the CIAC's decision but modified the awards for material costs and deleted awards for equipment/labor standby costs and unrealized profit. Both parties moved for reconsideration, which were denied. Hence, the parties filed their respective petitions for review on certiorari before the Supreme Court. The Petition: LICOMCEN questioned the CIAC's jurisdiction, arguing that FSI's claims were non-arbitrable and that FSI failed to comply with the condition precedent under GC-61. LICOMCEN also contested its liability for material costs, arguing FSI's delivery was in disregard of instructions and that FSI incurred no actual damage. FSI, in turn, questioned the CA's modification of the awards for material costs, deletion of standby costs, and unrealized profits.

Issue(s)

Whether the Construction Industry Arbitration Commission (CIAC) has jurisdiction over the dispute. Whether LICOMCEN's indefinite suspension of the Citimall project was valid. Whether LICOMCEN is liable for the material costs of the steel bars delivered. Whether FSI is entitled to equipment and labor standby costs. Whether FSI is entitled to unrealized profit, and whether nominal damages are warranted. Whether LICOMCEN should bear the costs of arbitration.

Ruling

The Supreme Court denied the petitions for review on certiorari of both LICOMCEN and FSI. The Court affirmed the CIAC's jurisdiction, modified the Court of Appeals' decision by including an award of nominal damages in favor of FSI, and ordered LICOMCEN to pay specific amounts for unpaid billings, material costs, and nominal damages, as well as the costs of arbitration.

Ratio Decidendi

On the jurisdiction of the CIAC: The Court held that the CIAC has original and exclusive jurisdiction over disputes arising from or connected with construction contracts, as provided by Executive Order No. 1008. This jurisdiction is broad and covers all disputes, including mere contractual money claims, and cannot be limited by stipulations in the contract that attempt to restrict its scope or impose conditions precedent. The Court emphasized that the mere existence of an arbitration clause in a construction contract is sufficient to vest the CIAC with jurisdiction. Therefore, LICOMCEN's argument that FSI's claims were non-arbitrable was rejected. On the validity of the indefinite suspension of the works: The Court found LICOMCEN's initial suspension of the works to be valid under GC-38 of the GCC, which allows suspension for various reasons including changes in design or pendency of cases. However, the Court ruled that LICOMCEN wrongfully prolonged the suspension. The Ombudsman case cited as a ground for suspension was dismissed in October 1998, yet LICOMCEN failed to inform FSI. Furthermore, LICOMCEN conducted a rebidding of the project without informing FSI, despite a notice from the City Government to proceed. This conduct indicated an intent to ease out FSI and terminate the contract, making the indefinite suspension invalid. On the claim for material costs at site: The Court upheld the CA's ruling that LICOMCEN is liable for only 50% of the cost of the steel bars. While GC-42(2) requires materials to be reasonably ordered, delivered to the contractor but not yet used, and certified by the Engineer, the Court found that FSI acted imprudently by proceeding with the delivery of steel bars after being informed of the suspension and design revisions. The delivery occurred after FSI received notices to suspend, and the argument that it was too late to stop the shipment was negated by the fact that the steel bars were loaded after the notices were received. The Court reasoned that FSI's imprudent action warranted limiting LICOMCEN's liability to 50% of the costs. On the claim for equipment and labor standby costs: The Court affirmed the CA's deletion of the award for equipment and labor standby costs. The CA found that FSI's presented lists of equipment and employees were insufficient to prove actual rental and maintenance expenses or salaries paid during the suspension. The Court agreed that lease contracts or receipts of payment were necessary to substantiate these claims, and in the absence of such evidence, the claim was denied as speculative. On the claim for unrealized profit and nominal damages: The Court denied FSI's claim for unrealized profit. While FSI argued that the prohibition under GC-41(2) applies only to lawful terminations, the Court found no distinction between "unrealized profit" and "anticipated profits" as defined in the contract. However, due to LICOMCEN's wrongful indefinite suspension and failure to observe proper termination procedures, the Court awarded FSI nominal damages of ₱100,000.00 to vindicate its right. On the liability for costs of arbitration: The Court agreed with the CA that LICOMCEN should bear the costs of arbitration. The Terms of Reference stipulated that costs would be divided, subject to determination. The CIAC found LICOMCEN at fault for its imprudent indefinite suspension, which caused the dispute. Therefore, LICOMCEN was ordered to pay the costs of arbitration.

Main Doctrine

The Construction Industry Arbitration Commission (CIAC) has original and exclusive jurisdiction over disputes arising from or connected with construction contracts, regardless of whether they involve mere contractual money claims or the execution of works. This jurisdiction cannot be diminished by stipulations in the contract that attempt to limit arbitrable disputes or impose conditions precedent not found in Executive Order No. 1008.

Access audio review, related cases, codal links, and more.

Open LexMatePH →