Rosa v. Bank of the Philippine Islands

G.R. No. 22359 · 1924-11-28 · J. ROMUALDEZ, J.: · Primary: Civil; Secondary: Commercial
REITERATION

Facts

The Antecedents: The defendant bank initiated a contest for designs and plans for a building, announcing that prizes would be awarded by November 30, 1921. The plaintiff participated in this contest, incurring work and expenses. The bank, however, failed to appoint judges and award the prizes by the stipulated date. Procedural History: The plaintiff filed an action seeking P30,000 in damages. The trial court rendered judgment ordering the defendant bank to pay P4,000 as indemnity and costs. Both parties appealed. The Appeal: The plaintiff appealed, arguing that the indemnity awarded was insufficient and that the bank should have been ordered to pay P30,000. The defendant bank appealed, contending that the date set for the award of prizes was not essential to the contract and that the P4,000 indemnity should not have been awarded.

Issue(s)

Whether the defendant bank was in default for failing to award the prizes on the stipulated date. Whether the date set for the award of prizes was an essential element of the contract.

Ruling

The Supreme Court reversed the judgment of the lower court, absolving the defendant bank entirely from the complaint. The Court found that the bank was not in default and that the plaintiff had no cause of action.

Ratio Decidendi

On Issue 1: The Court held that the defendant bank was not in default. According to Article 1100 of the Civil Code, default arises from the moment the creditor demands fulfillment of the obligation, either judicially or extrajudicially. The exceptions to this rule, where demand is not necessary, are when the obligor or the law expressly provides for it, or when, by the nature and circumstances of the obligation, the designation of the time for performance was the principal inducement to its creation. In this case, the plaintiff did not allege, nor did it appear, that any demand was made upon the bank before filing the action. Therefore, judicial or extrajudicial demand was necessary for default to arise. On Issue 2: The Court found that the date set for the award of prizes was not an essential element of the contract. While the plaintiff argued that the fixation of the price of concrete buildings at the time was the principal inducement, the Court reasoned that this fixation was likely for uniformity of designs and fair appreciation of works, not the primary reason for the contest's creation. The bank could not be certain that the price would remain current when it intended to construct the building. Citing Manresa, the Court explained that the 'principal inducement' must be judged on a case-by-case basis, and in this instance, the date was not the decisive factor that led to the obligation's creation. The Court also noted that evidence presented during the trial indicated the designs were being sent to New York for evaluation by a technical committee, suggesting the contest was proceeding, albeit with a delay in the award date.

Main Doctrine

The Supreme Court held that for a party to be in default (mora) in an obligation, a demand, either judicial or extrajudicial, is generally necessary. The exception to this rule, where demand is not needed, applies when the law or the obligor expressly provides for it, or when, by the nature and circumstances of the obligation, the designation of the time for performance was the principal inducement for its creation. In this case, the Court found that the date set for awarding prizes in a design contest was not the principal inducement, and thus, the bank was not in default merely by the lapse of time.

Access audio review, related cases, codal links, and more.

Open LexMatePH →