The President of the Church of Jesus Christ of Latter Day Saints v. BTL Construction Corporation

G.R. No. 176439 · 2014-01-15 · J. PERLAS-BERNABE, J.: · Primary: Commercial; Secondary: Civil
REITERATION

Facts

The Antecedents: The Church of Jesus Christ of Latter Day Saints (COJCOLDS) and BTL Construction Corporation (BTL) entered into a Construction Contract for the construction of a meetinghouse facility. The contract price was ₱12,680,000.00, with a completion period from January 15 to September 15, 2000. Due to various factors, including weather and plan revisions, the completion date was extended. On May 18, 2001, BTL, facing financial losses on another project, requested to bill COJCOLDS based on higher completion percentages and to execute deeds of assignment for its suppliers to collect payments directly. COJCOLDS granted this request. On August 13, 2001, BTL ceased operations due to lack of funds. COJCOLDS terminated the Contract on August 17, 2001, and hired another contractor, Vigor Construction, to complete the project. Procedural History: BTL filed a complaint before the Construction Industry Arbitration Commission (CIAC) claiming various amounts, including unpaid contract price, retention money, and damages. COJCOLDS filed a counterclaim for liquidated damages and reimbursement for payments made to BTL's suppliers. The CIAC partially granted both parties' claims. COJCOLDS was ordered to pay BTL the unpaid balance of the original contract price and additional works, while BTL was ordered to pay COJCOLDS liquidated damages and reimbursement for payments to suppliers. COJCOLDS appealed to the Court of Appeals (CA). The CA modified the CIAC ruling, ordering COJCOLDS to pay BTL the unpaid balance and retention money (less cost overrun), and BTL to reimburse COJCOLDS for overpayments on change orders. The CA also increased the liquidated damages awarded to COJCOLDS and deleted awards for additional works. Both parties moved for reconsideration, which were denied, leading to the consolidated petitions before the Supreme Court. The Petition: Both parties filed petitions for review on certiorari assailing the CA's decision and resolution.

Issue(s)

Whether the 10% retention money is separate from the unpaid balance of the contract price. Whether COJCOLDS is liable for the "additional works" performed by BTL, specifically the concrete retaining wall and works under Change Order Nos. 8 to 12. Whether BTL incurred delay and is liable for liquidated damages. Whether BTL is liable for cost overrun. Whether BTL received overpayments in the change orders and should reimburse COJCOLDS. Whether the parties are liable for each other's attorney's fees, arbitration costs, and costs of suit.

Ruling

The Supreme Court partly granted the petition of COJCOLDS (G.R. No. 176439) and denied the petition of BTL (G.R. No. 176718). The CA's decision was modified. COJCOLDS was ordered to pay BTL ₱1,612,017.74 as the unpaid balance of 98% of the contract price, inclusive of the 10% retention money. BTL was ordered to pay COJCOLDS ₱1,851,280.00 as liquidated damages, ₱526,400.00 as cost overrun, and ₱300,533.49 as reimbursement for overpayment in change orders. Each party was to bear its own costs.

Ratio Decidendi

On the 10% Retention Money and Unpaid Balance: The Court held that the 10% retention money is not a separate liability but a portion of the contract price withheld as security for corrective work. It forms part of the total contract price and should be automatically deducted from outstanding billings. Therefore, COJCOLDS's total liability to BTL was pegged at ₱1,612,017.74, representing the unpaid balance of 98% of the contract price, which already includes the retention money. This modified the CA's ruling that the retention money should be paid in addition to the unpaid balance. On Costs of Additional Works: The Court affirmed the CA's finding that COJCOLDS is not liable for the claimed additional costs for the concrete retaining wall and works under Change Order Nos. 8 to 12. For additional costs to be recoverable, Article 1724 of the Civil Code requires written authorization from the owner and a written agreement on the increased price. No such written authorization or agreement existed for the retaining wall, and it was considered part of the original plans. For Change Order Nos. 8 to 12, BTL had requested COJCOLDS to pay its suppliers directly, which COJCOLDS did, thus covering the costs and negating BTL's claim for additional payment. On Liquidated Damages Due to Delay: The Court upheld the CA's finding that BTL incurred delay. The architect recommended a total extension of 190 days. BTL failed to complete the project even with this extension, with the contract being terminated when the project was only 98% complete. The delay was reckoned from March 25, 2001, to August 17, 2001, totaling 146 days. Applying the contract provisions, BTL was liable for liquidated damages at ₱12,680.00 per day, resulting in a total of ₱1,851,280.00, modifying the CA's calculation of 142 days of delay. On Cost Overrun: The Court agreed with the CA that COJCOLDS incurred a cost overrun of ₱526,400.00 due to BTL's delay, which necessitated hiring another contractor to complete the project. BTL was ordered to reimburse COJCOLDS for this amount, consistent with the contract provisions allowing the owner to recover costs incurred due to the contractor's failure to complete the project. On Overpayments: The Court found that BTL was overpaid by ₱300,533.49 for works under Change Order Nos. 1 to 12. COJCOLDS paid a total of ₱1,315,003.28 for these works, which included payments to BTL's suppliers as requested by BTL. This amount exceeded what BTL charged for these modifications. BTL was obliged to return the overpaid amount based on Article 2154 of the Civil Code, which governs undue payments. On Attorney's Fees, Arbitration Costs, and Costs of Suit: The Court denied the award of attorney's fees to either party, finding no bad faith in their pursuit of claims. The fact that both the CIAC and CA found parts of their claims meritorious indicated a good faith dispute. Each party was ordered to bear its own arbitration costs and costs of suit.

Main Doctrine

The 10% retention money in construction contracts is a portion of the contract price withheld as security for corrective work and forms part of the total contract price, not a separate liability. Claims for additional works require written authorization and agreement on increased price. Liquidated damages are assessed based on the actual period of delay after accounting for valid extensions.

Access audio review, related cases, codal links, and more.

Open LexMatePH →