BF Corporation v. Werdenberg International Corporation

G.R. No. 174387 · 2015-12-09 · J. JARDELEZA, J.: · Primary: Commercial; Secondary: Civil
REITERATION

Facts

1. The Antecedents: BF Corporation (petitioner) and Werdenberg International Corporation (respondent) entered into a Construction Agreement for the construction of a three-story building for a meat processing plant and showroom. The agreed contract price was Php 43,800,000.00, with a completion date of April 7, 1995. Petitioner completed and turned over the building on August 15, 1995, but respondent refused acceptance due to alleged deficiencies. Respondent paid only Php 38,088,445.00, leaving a balance. Petitioner filed a complaint for the unpaid balance, plus expenses for additional orders and to contest respondent's claim for liquidated damages. 2. Procedural History: Petitioner initiated this case by filing a complaint for sum of money before the Pasig Regional Trial Court (RTC) against respondent for the unpaid balance of the contract price and expenses for additional works. The RTC ruled in favor of petitioner, ordering respondent to pay the outstanding balance, expenses for change orders, attorney's fees, and costs. On appeal, the Court of Appeals (CA) modified the RTC decision, holding respondent entitled to liquidated damages for 70 days of delay, a 10% retention fee, and payment for repainting expenses. The CA's decision was further modified on reconsideration to include the repainting expenses and retention fee in its computation. 3. The Petition: Petitioner seeks a reversal of the CA's resolution through a petition for review on certiorari under Rule 45 of the Revised Rules of Court. Petitioner argues that the CA misappreciated relevant facts and prays for the reinstatement of the RTC's decision. The core of the dispute revolves around the justifiable grounds for delays in the construction project, the extent of extensions to which petitioner is entitled, and consequently, the validity and amount of liquidated damages, retention fees, and expenses claimed by respondent.

Issue(s)

Whether the Court of Appeals erred in its computation of justifiable extensions of time for the delays encountered by the petitioner. Whether the Court of Appeals erred in holding the petitioner liable for liquidated damages. Whether the respondent is entitled to reimbursement for the repainting job. Whether the respondent is entitled to a 10% retention fee.

Ruling

The Supreme Court partly granted the petition, modifying the Court of Appeals' resolution. The Court determined the total justifiable extension for petitioner to be 112 days. Consequently, petitioner was in default for 18 days, entitling respondent to liquidated damages of Php 788,400.00. The Court also affirmed respondent's entitlement to expenses for the repainting job (Php 1,050,000.00) and the 10% retention fee. The final award to petitioner was adjusted accordingly.

Ratio Decidendi

On the computation of justifiable extensions of time: The Supreme Court found that the Court of Appeals erred in its computation of justifiable extensions. The Court meticulously reviewed the delays, granting petitioner a 21-day extension for excavation works, considering the unforeseen concrete slabs and soft soil conditions, but also accounting for petitioner's fault in equipment breakdown and manpower issues. For the delay in securing the building permit and the stop-work order, the Court granted an extension of 38 days, holding respondent responsible for failing to initiate the ECC application as per the pre-bid conference minutes and for the revisions to the building plan. An extension of 40 days was granted for change orders and extra works, acknowledging admissions from respondent's witness and partial payments made. Additionally, 7 days were granted for a work stoppage due to a boundary dispute, and 6 days for holidays. In total, the Court determined petitioner was entitled to a 112-day extension. On the liability for liquidated damages: Based on the established 112-day justifiable extension, the Supreme Court calculated that petitioner was in default for 18 days (from July 28, 1995, to August 15, 1995). The contract stipulated Php 43,800.00 per day of delay. Therefore, respondent was entitled to liquidated damages amounting to Php 788,400.00 (18 days x Php 43,800.00). This amount was deducted from the total amount due to petitioner, modifying the CA's award of Php 3,066,000.00 for 70 days of delay. On the entitlement to expenses for the repainting job: The Supreme Court affirmed the CA's ruling that respondent was entitled to reimbursement for the repainting job. The Court found that defects in the painting job were due to poor workmanship, which petitioner acknowledged and guaranteed under the contract for one year. When petitioner failed to remedy these defects, respondent was justified in hiring another contractor. Citing Article 1167 of the Civil Code, the Court held that if an obligor fails to perform an obligation, it shall be executed at his cost, and if done poorly, it may be undone. The expenses incurred by respondent for the repainting job, amounting to Php 1,050,000.00, were thus affirmed. On the entitlement to a 10% retention fee: The Supreme Court upheld the CA's decision granting respondent the 10% retention fee. Citing H.L. Carlos Construction, Inc. v. Marina Properties Corporation, the Court explained that the 10% retention money is standard practice in the construction industry, serving as security for corrective work. Section 14 of the Construction Agreement outlined the conditions for its release, which petitioner had complied with. Therefore, respondent was entitled to retain this amount as security.

Main Doctrine

The Supreme Court modified the Court of Appeals' decision, partly granting the petition and modifying the award of damages. The Court determined the justifiable extensions of time for delays, calculated the actual number of days of default, and adjusted the amounts for liquidated damages, expenses for repainting, and retention fee, ultimately modifying the total amount due to the petitioner.

Access audio review, related cases, codal links, and more.

Open LexMatePH →