Philippine Economic Zone Authority v. Pilhino Sales

G.R. No. 185765 · 2016-09-28 · J. LEONEN, J.: · Primary: Civil; Secondary: Commercial
REITERATION

Facts

1. The Antecedents: The Philippine Economic Zone Authority (PEZA) entered into a contract with Pilhino Sales Corporation (Pilhino) for the acquisition of two fire trucks. The contract stipulated a delivery period of 45 days from receipt of a purchase order and a penalty of 1/10 of 1% of the total contract price for each day of delay. Pilhino failed to deliver the fire trucks within the agreed timeframe, prompting PEZA to demand compliance. Despite these demands, Pilhino remained non-compliant, leading PEZA to file a complaint for rescission of contract and damages. 2. Procedural History: The Regional Trial Court (RTC) of Pasay City ruled in favor of PEZA, ordering Pilhino to pay liquidated damages at the stipulated rate, exemplary damages, and to have the contract rescinded with forfeiture of its performance bond. Pilhino appealed this decision to the Court of Appeals (CA). The CA partly granted Pilhino's appeal, reducing the liquidated damages and deleting the forfeiture of the performance bond. PEZA sought reconsideration of the CA's modifications, but its motion was denied. Consequently, PEZA filed the present Petition for Review on Certiorari before the Supreme Court. 3. The Petition: Petitioner PEZA seeks the reinstatement of the RTC's decision, arguing that it suffered damages due to Pilhino's delay and that the contractually stipulated liquidated damages were reasonable and freely agreed upon. PEZA contends that the CA's computation of damages lacked factual and legal basis and that Pilhino's subsequent offer to modify the contract was inconsequential as it was made after the filing of the complaint and undermined the integrity of the public bidding process. Respondent Pilhino, conversely, questions whether a rescinded contract can still give rise to liability for liquidated damages stipulated within it, suggesting that rescission should negate such penalties.

Issue(s)

Whether contractually stipulated liquidated damages can be given effect despite the rescission of the contract. Whether the Court of Appeals erred in reducing the amount of liquidated damages.

Ruling

The Supreme Court granted the Petition, reversed the Court of Appeals' Decision and Resolution, and reinstated the Regional Trial Court's Decision.

Ratio Decidendi

On the first issue: The Court held that the rescission of a contract under Article 1191 of the Civil Code does not necessarily obliterate the liability for contractually stipulated liquidated damages. Article 1191 explicitly states that the injured party may choose between fulfillment and rescission, "with the payment of damages in either case." The breach or delay that triggers rescission is the same event that makes damages due. When parties freely agree on liquidated damages, this agreement establishes the law between them. To allow the negation of liquidated damages upon rescission would enable contractual breach to become a profitable enterprise and an evasion of consequences, which is an injustice the Court cannot tolerate. The Court cited Laperal v. Solid Homes, Inc. to support the principle that stipulated damages can be maintained alongside rescission. On the second issue: The Court found the Court of Appeals in error for reducing the liquidated damages. The Court emphasized that Pilhino's offer to provide new specifications at a higher price, made after the Complaint for rescission and damages had already been filed, was inconsequential and not a valid remedy. This offer came too late and under circumstances where PEZA was no longer in a position to accept modifications, especially considering the contract was awarded through public bidding. The Court reiterated that modifying awarded contracts after public bidding destroys the essence of fair competition. The Court noted that PEZA had an urgent need for the fire trucks, and Pilhino's delay exposed PEZA's operations to risk. Therefore, the Court reinstated the RTC's award of liquidated damages based on the contractually stipulated penalty.

Main Doctrine

Contractually stipulated liquidated damages are generally maintained even in cases of rescission of contract due to breach, as rescission under Article 1191 of the Civil Code is accompanied by the payment of damages, and the parties' agreement on liquidated damages reflects their own volition. However, such damages are subject to equitable reduction under Articles 1229 and 2227 of the Civil Code.

Access audio review, related cases, codal links, and more.

Open LexMatePH →