Philippine Science High School-Cagayan Valley Campus v. Pirra Construction Enterprises

G.R. No. 204423 · 2016-09-14 · J. DEL CASTILLO, J.: · Primary: Commercial; Secondary: Civil, Remedial
REITERATION

Facts

1. The Antecedents: This case involves a dispute between PIRRA Construction Enterprises (PIRRA) and the Philippine Science High School-Cagayan Valley Campus (PSHS) concerning two construction projects: Project A and Project C. PIRRA, a contractor, entered into agreements with PSHS for the construction of various buildings and facilities. For Project A, PIRRA was awarded contracts for an Academic Building and a Girls' Dormitory. For Project C, PIRRA was contracted for an Academic Building II, Boys' Dormitory, and a School Canteen. Disputes arose regarding payments, project completion, alleged delays, and contract terminations for both projects. 2. Procedural History: PIRRA initiated a complaint with the Construction Industry Arbitration Commission (CIAC) against PSHS, seeking damages related to both Project A and Project C. The CIAC rendered a Final Award in favor of PIRRA, holding PSHS liable for delays in payment for Project A's Partial Billing No. 5 and for the unjustified takeover of Project A. The CIAC also found PSHS liable for delays in submitting revised drawings and issuing a variation order for Project C, leading to wrongful termination. PSHS appealed this award to the Court of Appeals (CA). The CA modified the CIAC's award, partially granting PSHS's petition, reducing some monetary awards, and deleting others, while affirming some aspects of the CIAC's decision. PSHS then filed a Petition for Review on Certiorari with the Supreme Court. 3. The Petition: PSHS filed a Petition for Review on Certiorari under Rule 45 of the Rules of Court, assailing the CA's decision and resolution. PSHS argued that the CA erred in its findings of fact, specifically regarding PSHS's alleged treatment of Project A as substantially completed and its subsequent liability for the residual value of Partial Billing No. 5. PSHS also contended that the CA erred in holding it liable for the value of work done on Project C, despite its claim of valid termination, and for fabricated materials. Furthermore, PSHS disputed the award of attorney's fees and argued that its government funds are exempt from execution. PIRRA, in its response, countered that PSHS's actions constituted a substantial completion of Project A and an invalid termination of Project C, entitling PIRRA to damages and attorney's fees.

Issue(s)

Whether the Court of Appeals erred in finding that PSHS treated Project A as substantially completed such that PSHS is liable for the residual value of Partial Billing No. 5. Whether PSHS validly terminated the contract for Project C. Whether PSHS is liable for the value of the fabricated steel bars, steel awning windows with security grills and steel railings, and whether PIRRA is entitled to compensation for the value of work done on Project C (quantum meruit) and whether the CA erred in its computation. Whether PIRRA is entitled to moral and exemplary damages and attorney's fees. Whether PSHS' funds are exempt from execution.

Ruling

The Petition is DENIED. The Decision dated January 20, 2012 and Resolution dated July 23, 2012 of the Court of Appeals in CA-G.R. SP No. 118152 are AFFIRMED with MODIFICATION that the monetary awards shall earn interest at the rate of six percent (6%) per annum from the time the awards became final until full payment. The Supreme Court upheld CA's computation of the net residual value of Partial Billing No. 5 (P706,077.29), affirmed award of the value of work done on Project C (P1,019,399.59) and the value of fabricated items (P202,925.18), and affirmed award of attorney's fees; deleted awards for moral and exemplary damages as modified by the CA.

Ratio Decidendi

On Whether PSHS treated Project A as substantially completed: The Supreme Court sustained the factual finding of the CIAC and the CA that PSHS treated Project A as substantially completed. The Court relied on PSHS' own conduct: PSHS acted on PIRRA's request for substantial acceptance, created an Inspectorate Team to perform a punch listing, and repeatedly referred to PB No. 5 as the final billing. The CIAC correctly held that a COA inspection is not a condition precedent to payment of a progress billing; therefore, COA findings could not justify refusal to pay for performed items. Applying Article 1234 of the Civil Code, the Court recognized that where an obligation has been substantially performed in good faith, the performer may recover as if fully performed less damages; accordingly the Court approved the CA's deduction of defective items and the net computation of PB No. 5. Given that the CIAC and CA findings on these facts were supported by the record and the CIAC's expertise, the Supreme Court accorded finality to those findings and declined to disturb them. The net result is affirmation of PSHS' liability to pay the computed residual amount of PB No. 5 as modified by the CA. On Whether PSHS validly terminated the contract for Project C: The Court affirmed the CA's conclusion that PSHS validly terminated the Project C contract. The Court reconciled conflicting findings by observing that both parties failed to comply with their November 20, 2009 Agreement: while PSHS may have not timely submitted revised drawings, PIRRA also ceased coordination, refused communications, and suspended work on October 12, 2009 without PSHS' approval. Under the General Conditions of Contract quoted by the Court (Termination for Default of Contractor; provisions on negative slippage, abandonment, failure to comply with instructions), PIRRA's unauthorized suspension, delay and alleged abandonment constituted sufficient grounds for termination. The Court emphasized that both the CIAC and CA made distinct fact findings; because the CA's conclusion that PIRRA suspended work prior to the November 20 Agreement was supported by the record, termination was valid. The Supreme Court therefore upheld PSHS' right to terminate for default while still addressing equitable compensation for work performed. On Whether PSHS is liable for fabricated items and value of work on Project C: The Court sustained the CIAC and CA findings that PSHS is liable for the value of fabricated steel bars, awning windows with grills and railings, and must pay for the work done on Project C to avoid unjust enrichment. Applying the doctrine of quantum meruit, the Court held that PIRRA is entitled to payment for the 25.25% accomplishment on Project C because it would be unjust for PSHS to retain benefits without payment. The Court deferred to the CIAC's technical findings regarding fabricated items because of CIAC's specialized expertise in construction disputes and found no competent evidence of misappreciation of facts. Because CA's valuation and technical acceptance of the fabricated items and the percentage accomplishment were supported by evidence, the Supreme Court declined to disturb those awards. The Court ordered PSHS to pay the amount computed by the CA for the work done and fabricated items. On Moral and Exemplary Damages and Attorney's Fees: The Supreme Court affirmed the CA's deletion of moral and exemplary damages, finding no legal basis to sustain those awards given the record and CA analysis. However, the Court affirmed the award of attorney's fees to PIRRA because it was compelled to litigate/arbitrate to recover what was due and to protect its contractual interests, applying settled jurisprudence awarding attorney's fees when claimants are forced to file suits to recover rightful dues. The Supreme Court thus sustained attorney's fees as affirmed by the CA but removed moral and exemplary damages as modified by the CA. On Exemption of Government Funds from Execution: The Court rejected PSHS' contention that government funds are immune from execution in this context, reasoning that PSHS, having accepted and benefited from PIRRA's services, must pay for them; failure to do so would cause grave injustice and unjust enrichment. The Court therefore denied the claim of immunity from execution insofar as enforcement of final monetary awards is concerned.

Main Doctrine

Deference to factual findings of quasi-judicial bodies (CIAC) affirmed; application of quantum meruit and prevention of unjust enrichment in payment for partially completed government construction works; CA's modification of monetary awards sustained, with interest at 6% per annum from finality.

Access audio review, related cases, codal links, and more.

Open LexMatePH →