Department of Public Works and Highways v. CMC/Monark/Pacific/Hi-Tri Joint Venture

G.R. No. 179732 · 2017-09-13 · J. LEONEN, J.: · Primary: Commercial; Secondary: Civil
REITERATION

Facts

The Antecedents: The Department of Public Works and Highways (DPWH) and CMC/Monark/Pacific/Hi-Tri Joint Venture (Joint Venture) entered into a Contract for the Construction of Contract Package 6MI-9. During the project's execution, the Joint Venture's equipment was set on fire, and a bomb exploded at its hatching plant, attributed to MILF members. The Joint Venture made demands for extension and payment of the foreign component of the contract. BCEOM French Engineering Consultants recommended prompt payment. The project was reportedly 80% complete when halted. Procedural History: The Joint Venture filed a complaint before the Construction Industry Arbitration Commission (CIAC) for various claims. Subsequently, the parties mutually terminated the contract. CIAC rendered an Award ordering DPWH to pay the Joint Venture's money claims with legal interest, but denied the claim for price adjustment under Presidential Decree No. 1594. Both parties appealed to the Court of Appeals (CA). The CA affirmed CIAC's Award with modifications, remanding the case to CIAC for determination of time extensions and conversion rates. The CA also ruled that the mutual termination did not render the case moot and academic but modified the award regarding payment in US dollars. The Petition: DPWH filed a Petition for Review on Certiorari with the Supreme Court, assailing the CA Decision. The issues raised included whether the case was moot and academic, premature due to non-exhaustion of administrative remedies, and the entitlement to various claims, including the foreign component, time extensions, price adjustments, equipment and financial losses, and interest.

Issue(s)

Whether the mutual termination of the Construction Contract rendered the arbitration proceedings moot and academic. Whether the Joint Venture complied with the doctrine of exhaustion of administrative remedies. Whether the CIAC findings regarding the entitlement to the foreign component and time extensions are subject to review by the Supreme Court. Whether the DPWH is liable for equipment losses resulting from the bombing incident under the contract's 'Employer's Risk' clause.

Ruling

The Supreme Court denied the petition, affirming the Court of Appeals Decision with modification. The Court reversed the order remanding the case to CIAC for being moot and academic and pegged the legal interest rate at twelve percent (12%) per annum until June 30, 2013, and then at six percent (6%) per annum until full satisfaction.

Ratio Decidendi

On Issue 1: The Court ruled that the case was not moot because there remained an unresolved justiciable controversy regarding the payment for work already accomplished. Following the principle in Carpio v. Court of Appeals, the mutual termination of a contract does not automatically dissolve the obligation to settle outstanding financial liabilities incurred during the life of the agreement. The Joint Venture explicitly reserved its right to these claims in its termination request, which the DPWH Acting Secretary accepted. To dismiss the case as moot would allow the government to be unjustly enriched by work done without compensation. Therefore, the resolution of these monetary issues provides practical value and substantial relief to the parties. On Issue 2: The Joint Venture did not violate the doctrine of exhaustion of administrative remedies. Although Clause 67.1 of the Conditions of Contract required reference to the Engineer, the Joint Venture had sent 17 demand letters, including four to the DPWH Secretary, which were ignored for years. Under the law, strict application of the doctrine is set aside when requiring further administrative action would be an 'exercise in futility' or unreasonable under the circumstances. Given the continuous financial suffering of the Joint Venture and the DPWH's silence, the Joint Venture was justified in seeking immediate relief through the CIAC. The tribunal correctly found that the procedural requirements for dispute settlement were substantially complied with. On Issue 3: Factual findings of the CIAC are accorded respect and finality by the Supreme Court, especially when affirmed by the Court of Appeals. The DPWH’s arguments regarding the foreign component and Letter of Credit (LC) renewal were factual in nature and did not fall under the limited exceptions for Rule 45 review. The Court noted that the DPWH's own refusal to grant contract extensions prevented the Joint Venture from renewing the LC, meaning the DPWH could not use the lack of a renewed LC as a defense against payment. Applying National Housing Authority v. First United Constructors Corp., the Court held it would not re-examine evidence where the CIAC’s findings were supported by the record. The expertise of the CIAC in construction matters ensures that its determinations on technical issues, such as slippage and mobilization, are reliable. On Issue 4: The bombing incident and equipment losses are compensable as 'Employer's Risks' under Clause 20.4 of the Conditions of Contract. This clause specifically identifies rebellion, revolution, insurrection, and civil war as risks assumed by the employer (DPWH). Evidence presented before the CIAC, including police reports and operator testimonies, sufficiently established that the losses were caused by MILF members. Furthermore, the DPWH failed to specifically deny these allegations in its answer, as required under Rule 8, Section 10 of the Rules of Court. A general denial, even if it uses the word 'specifically,' is insufficient to overcome proven factual claims of property destruction in a conflict zone.

Main Doctrine

The mutual termination of a construction contract does not render the dispute moot and academic, as unresolved claims and obligations remain justiciable. Findings of fact by the Construction Industry Arbitration Commission (CIAC), when affirmed by the Court of Appeals, are accorded respect and finality, barring compelling reasons to the contrary.

Access audio review, related cases, codal links, and more.

Open LexMatePH →