Metro Rail Transit v. Gammon Philippines

G.R. No. 200401 · 2018-01-17 · J. LEONEN, J.: · Primary: Commercial; Secondary: Civil
REITERATION

Facts

The Antecedents: Metro Rail Transit Development Corporation (MRT) invited Gammon Philippines, Inc. (Gammon) to bid for the concrete works of the MRT-3 North Triangle Description Project's Podium. Gammon won the bid, and Parsons Interpro JV (Parsons), the management team, issued a Letter of Award and Notice to Proceed (First Notice to Proceed) on August 27, 1997. Gammon signed and returned the First Notice to Proceed on September 2, 1997, and submitted the contract documents on September 9, 1997. However, on September 8, 1997, MRT sent a letter indicating a need for a week or two to assess the effects of foreign exchange rate developments before issuing a formal Notice to Proceed. Parsons then directed Gammon to hold further mobilization activities. Subsequently, MRT decided to downscale the Podium's construction and proceed with a conceptual redesign. Gammon was asked to re-design, leading to a Second Notice to Proceed for engineering services on February 18, 1998. MRT issued a Third Notice to Proceed on April 2, 1998, which was temporarily rescinded. On June 11, 1998, MRT issued a Fourth Notice to Proceed, expressly canceling the First and Third Notices. Gammon qualifiedly accepted the Fourth Notice, which MRT treated as a new offer and rejected. Gammon then notified MRT of its claims for reimbursement and damages due to mobilization, suspension orders, and the consequences of awarding the contract to another party. Procedural History: Gammon filed a Notice of Claim before the Construction Industry Arbitration Commission (CIAC) against MRT. MRT moved to dismiss, arguing lack of jurisdiction, but this was denied. This Court, in Gammon v. Metro Rail Transit Development Corporation, held that CIAC had jurisdiction. MRT filed its Answer, expressing willingness to pay ₱5,493,639.27 for engineering/design services and site de-watering/clean-up. The Arbitral Tribunal was formed, and CIAC ruled in favor of Gammon, awarding ₱4,821,261.91 for engineering services, ₱672,377.36 for site de-watering and clean-up, and ₱53,149,330.35 for lost profits, totaling ₱58,642,969.62. The Court of Appeals affirmed the CIAC Decision. MRT filed the present Petition for Review on Certiorari. The Petition: MRT assails the Court of Appeals' Decision, arguing that no perfected contract existed between the parties, Gammon's claim for lost profits was unsubstantiated, and reimbursements were not supported by official receipts. MRT also contends it is not estopped from contradicting its alleged judicial admission of liability for reimbursements and is entitled to attorney's fees.

Issue(s)

Whether a perfected contract exists between MRT and Gammon. Whether the doctrine of the law of the case applies based on the prior ruling in Gammon v. Metro Rail Transit Development Corporation. Whether MRT is bound by its allegation in its Answer with Compulsory Counterclaim regarding its willingness to pay ₱5,493,639.27. Whether Gammon's claims for actual damages, reimbursements, and lost profits were sufficiently proven.

Ruling

The Petition is DENIED. The Court of Appeals October 14, 2011 Decision and January 25, 2012 Resolution in CA-G.R. SP No. 98569 are AFFIRMED.

Ratio Decidendi

On the existence of a perfected contract: The Court held that a perfected contract exists between MRT and Gammon. A contract is perfected by the meeting of the minds of the parties on the object and cause, which occurs upon absolute acceptance of an offer. The First Notice to Proceed, issued by Parsons on behalf of MRT, constituted an award and acceptance of Gammon's bid. Gammon's subsequent actions, including signing and returning the First Notice to Proceed, mobilizing resources, and preparing bonds, demonstrated its concurrence and acceptance. The Court clarified that the failure to sign the formal contract documents does not negate the contract's perfection, as the award itself perfects the contract upon notice. The subsequent actions by MRT, such as the "temporary suspension" of work and the issuance of a Fourth Notice to Proceed expressly canceling prior notices, implied the existence of a subsisting contract that was being modified or terminated, rather than an absence of a contract from the outset. The Court emphasized that the perfection of the contract was not one-sided and bound both parties. On the application of the doctrine of the law of the case: The Court ruled that the doctrine of the law of the case applies. In Gammon v. Metro Rail Transit Development Corporation, this Court determined that CIAC had jurisdiction because the parties entered into a construction contract with an agreement to arbitrate. The Court found that the redesign and price reduction merely modified the contract, rather than constituting a novation that would extinguish the original agreement. This prior determination that the contract was modified, not extinguished, and that an arbitration clause remained in effect, governs the present case regarding the existence of a contract and the applicability of the arbitration clause. The Court reiterated that CIAC's jurisdiction is over disputes arising from construction contracts, not over the contracts themselves, and this jurisdiction persists even if the contract is breached, abandoned, terminated, or rescinded. On MRT's judicial admission: The Court affirmed that MRT is bound by its judicial admission in paragraph 77 of its Answer with Compulsory Counterclaim, wherein it expressed willingness to pay ₱5,493,639.27 for engineering/design services and site de-watering/clean-up. The Court found that this admission was unqualified and was not accompanied by any statement requiring Gammon to first present official receipts or proof of payment. MRT did not amend its Answer to correct or qualify this admission. Under Rule 129, Section 4 of the Revised Rules of Court, a judicial admission can only be contradicted by showing palpable mistake or that no such admission was made, neither of which was demonstrated by MRT. Therefore, MRT is estopped from denying its representation. On the sufficiency of proof for claims: The Court upheld the CIAC's and Court of Appeals' findings regarding the sufficiency of Gammon's claims. For reimbursements, the Court noted that while official receipts are the best evidence, actual damages can be proven by other documentary evidence like invoices and debit notes, which Gammon provided. The Court found that MRT failed to prove the insufficiency of Gammon's evidence or the erroneousness of its computations. For lost profits, the Court affirmed the award based on the testimony of Francisco Delos Santos, Gammon's Planning and Estimating Engineer, who testified on the industry standard profit percentage. The Court reiterated that arbitration proceedings are not bound by strict technical rules of evidence and that factual findings of CIAC, a specialized body, are accorded respect and finality, especially when affirmed by the Court of Appeals. The Court found no grave abuse of discretion or any of the recognized exceptions that would warrant disturbing CIAC's factual findings.

Main Doctrine

A contract is perfected by the meeting of the minds of the parties on the object and cause thereof, which occurs upon the offer and absolute acceptance. The award of a contract to a bidder, communicated to the bidder, perfects the contract, and subsequent modifications or temporary suspensions do not negate its perfection, nor does the failure to sign the formal contract affect its existence. Furthermore, judicial admissions made in pleadings, if not proven to be palpable mistakes, are binding on the party making them.

Access audio review, related cases, codal links, and more.

Open LexMatePH →