Land Bank v. Megaworld

G.R. Nos. 193893-94 · 2019-10-09 · J. BERSAMIN, J.: · Primary: Commercial; Secondary: Civil
REITERATION

Facts

The Antecedents: Land Bank of the Philippines (Landbank) and Megaworld Corporation (Megaworld) entered into a property development contract for the construction of Landbank's corporate headquarters. Megaworld notified Landbank of the project's completion, but Landbank did not issue a certificate of completion and acceptance, releasing only a portion of the retained money. Megaworld demanded payment for the balance, retention money, and various change orders and rectification works. Landbank denied liability for some change orders and counterclaimed for costs incurred in completing the project due to Megaworld's delay in correcting defects, seeking reimbursement and damages. Procedural History: The parties submitted their dispute to the Construction Industry Arbitration Commission (CIAC). Landbank's offer of additional documents was initially denied for violating arbitration rules but later admitted upon reconsideration. The CIAC rendered an award in favor of Megaworld, which was later amended. Both parties appealed to the Court of Appeals (CA). The CA modified the net award in favor of Megaworld. Landbank appealed to the Supreme Court. The Petition: Landbank appealed to the Supreme Court, questioning the CA's deletion or reduction of certain amounts awarded to it in its counterclaim, specifically concerning rectification costs for parking area slopes, electrical works for the telephone system, and curtain walls. Landbank also questioned the CA's upholding of the CIAC ruling on the balance of the original contract price and the application of temperate damages and Article 1724 of the Civil Code.

Issue(s)

Whether the Court of Appeals committed reversible error in deleting the total amount of P16,200,000.00 representing the CIAC computed claim for rectification costs for the slope to drain concrete topping at parking areas and deck slab in favor of Land Bank. Whether the Court of Appeals committed reversible error when it materially reduced the CIAC awarded claim of Land Bank on the rectification of the glass curtain walls and in upholding the denial of the claim for the fees of the consultant. Whether the Court of Appeals committed reversible error when it deleted the CIAC awarded claim of Land Bank for the cost of electrical work for the telephone system in the amount of P4,717,619.28. Whether the Court of Appeals properly committed reversible error when it upheld the CIAC ruling awarding the amount of PHP58,507,095.16 to Megaworld as the balance of the original contract price despite the failure on the part of Megaworld to attain 100% completion. Whether the Court of Appeals properly applied the law on temperate damages on Megaworld's claim for forced suspension of work in the amount of PHP2,520,000.00. Whether the Court of Appeals properly applied Article 1724 of the New Civil Code on the matter of Land Bank's claim for specific rectification and other costs. Whether the Court of Appeals properly interpreted the contract particularly on the Contractors All Risk Insurance (CARI) coverage when it denied Land Bank's claim for the earthquake damage on walls amounting to PHP4,753,017.79.

Ruling

The Supreme Court partially granted the petition for review on certiorari, affirming the CA decision with modifications. The Court reinstated the award to Landbank for electrical works for the telephone system and the costs of rectification works on the slope of parking areas. The case was remanded to the CIAC for the proper determination of Megaworld Corporation's liability for these costs.

Ratio Decidendi

On the deletion of P16,200,000.00 for rectification costs on parking area slopes (Item 3): The Court found that while the CIAC's award of P16,200,000.00 was based on an unsupported rate of P450.00/square meter, and the CA correctly noted the procedural issue regarding the belated submission of documents, the admission by Megaworld of responsibility for the "water ponding" issue could not be ignored. Therefore, Megaworld's obligation to compensate Landbank for rectification works was established, though the exact amount remained undetermined. The Court reinstated this award, remanding the case to the CIAC for the proper determination of the extent of Megaworld's liability. On the reduction of rectification costs for curtain walls, etc. (Item 1): The Court found no reversible error in the CA's modification of the CIAC's award for rectification works on curtain walls, etc. The CA adjusted the amount because the CIAC had not specified the source of the base amount used in its computation and had erroneously deducted disapproved consultancy service fees. The CA's reduction was deemed equitable and proper. On the deletion of P4,717,619.28 for electrical works for the telephone system (Item 2): The Court disagreed with the CA's deletion of this cost. While acknowledging that there was no explicit agreement by Megaworld authorizing the deduction, the Court noted that the CIAC had considered the general practice in the construction industry where telephone utility, not the building contractor, provides materials for telephone system electrical works. The CIAC also observed Megaworld's non-objection to the deduction, which it considered acquiescence. The Court reinstated this award, remanding the case to the CIAC for the proper determination of the extent of Megaworld's liability. On the balance of the original contract price: The Court noted that Landbank challenged factual findings regarding the contract balance, which is generally disallowed in a petition for review on certiorari. The Court stated that the factual findings of the CIAC, affirmed by the CA, were conclusive. Therefore, the CA's upholding of the CIAC ruling on this matter was sustained. On temperate damages for forced work suspension: The Court did not explicitly rule on this issue in the dispositive portion, but it was part of the issues raised by Landbank. The CA had modified the award related to this claim, and the Supreme Court's decision focused on the counterclaims. The absence of a specific ruling on this issue in the dispositive portion implies it was either affirmed as modified by the CA or not disturbed. On Article 1724 of the New Civil Code: Similar to the issue on temperate damages, the Court did not provide a specific ratio for this particular issue in the dispositive portion. The issues raised by Landbank under this article pertained to specific claims for rectification and other costs, which were largely addressed by the Court's rulings on the reinstatement or modification of the CIAC and CA awards concerning Landbank's counterclaims. On CARI coverage for earthquake damage: The Court did not provide a specific ratio for this issue in the dispositive portion. This was one of the issues raised by Landbank, but the Court's focus was on the modifications and remands concerning the counterclaims.

Main Doctrine

The Supreme Court may review factual findings of the CIAC and CA when the CA disagrees with the CIAC's factual findings. However, the Court generally defers to the technical expertise of the CIAC and the CA's factual findings when affirmed by the CA. In cases involving the determination of costs for rectification works and deductive costs, where the CA's findings differ from the CIAC's, the Court may reinstate or remand the case for proper determination of liability.

Access audio review, related cases, codal links, and more.

Open LexMatePH →