De Castro v. Commission on Audit

G.R. No. 228595 · 2020-09-22 · J. GAERLAN, J.: · Primary: Political; Secondary: Taxation, Administrative Law
REITERATION

Facts

The Antecedents: This case concerns the construction of the Bulan Integrated Bus Terminal (BIBT) and Bulan Slaughterhouse projects in the Municipality of Bulan, Sorsogon. The projects were authorized by Sangguniang Bayan Ordinance No. 004, Series of 2003, which allowed for a bond flotation of up to P50,000,000.00. Public biddings were conducted in October 2006, leading to contracts awarded to S.R. Baldon Construction & Supply for the BIBT (P32,984,700.00) and Steven Construction & Supply for the Slaughterhouse (P4,991,800.00). Following the payment for these projects, a special audit was initiated, resulting in several Notices of Disallowance (NDs) issued by the Commission on Audit (COA) for various alleged deficiencies, including unaccomplished work, overpricing, liquidated damages for delays, and violations of procurement procedures. Procedural History: The initial Notices of Disallowance (NDs) were issued by the COA's Audit Team Leader, covering multiple aspects of the construction projects. Petitioners, including former Municipal Mayor Helen C. de Castro and other municipal officials, along with private contractors, appealed these NDs to the COA Regional Office No. V. The Regional Director issued a decision on June 4, 2012, partially granting the appeal and modifying some of the disallowances. This decision was then elevated to the COA Proper for automatic review. On September 11, 2014, the COA Proper issued a decision affirming with modification the Regional Director's ruling. A motion for reconsideration filed by the petitioners was denied by the COA in a Resolution dated November 9, 2016. Aggrieved by these decisions, the petitioners filed the present petition for certiorari. The Petition: The petitioners seek to annul and set aside the COA Decision dated September 11, 2014, and the COA Resolution dated November 9, 2016, through a petition for certiorari under Rule 65, in relation to Rule 64 of the Rules of Court. They argue that the COA committed grave abuse of discretion amounting to lack or excess of jurisdiction. Specifically, they contend that the COA erred in disallowing certain amounts based on incorrect legal interpretations, such as the validity of a work suspension order, the application of equipment rental rates, and the imposition of liability for alleged misfeasance. They also raise procedural issues, including alleged violations of their right to speedy disposition of cases and due process due to delays in resolution and the manner in which arguments were addressed. The petition also challenges the COA's pronouncements on administrative liability for violations of the Government Procurement Reform Act (RA 9184) despite lifting the related disallowances.

Issue(s)

Whether the petition for certiorari was filed within the reglementary period. Whether petitioners were denied their right to speedy disposition of their case. Whether petitioners were denied administrative due process. Whether ND No. 2008-06-27-001-101 (2009) for unaccomplished deficiency/liquidated damages was validly sustained in part. Whether ND No. 2008-06-27-002-101 (2009) for overpricing and overestimation of quantities was validly sustained in part. Whether ND No. 2008-06-27-003-101 (2009) for liquidated damages due to work suspension was validly imposed on Mayor De Castro. Whether ND No. 2008-06-27-004-101 (2009) for liquidated damages due to alleged misfeasance of the Municipal Engineer was validly imposed. Whether ND Nos. 2008-06-27-005-101 (2009) and 2008-06-27-006-101 (2009) for failure to post on PhilGEPS were validly lifted, and whether administrative liability could still be imposed.

Ruling

The Supreme Court partially granted the petition, modifying the assailed COA Decision and Resolution. The Court affirmed the modified ND No. 2008-06-27-001-101 (2009) holding Shirley R. Baldon liable for P145,770.60 in liquidated damages. It sustained the partial lifting of ND No. 2008-06-27-002-101 (2009) but clarified the amounts, holding BAC Chairman Dennis H. Dino and Municipal Engineer Toby C. Gonzales, Jr. liable for the remaining P1,857,875.33 for overestimation in quantity. The Court affirmed the lifting of ND No. 2008-06-27-003-101 (2009) for liquidated damages, setting aside the imposition of liability on Mayor De Castro. It also affirmed the lifting of ND No. 2008-06-27-004-101 (2009) but warned Municipal Engineer Gonzales against giving inconsistent information. The lifting of ND Nos. 2008-06-27-005-101 (2009) and 2008-06-27-006-101 (2009) for failure to post on PhilGEPS was affirmed for lack of legal basis, but without prejudice to the administrative liability of Mayor De Castro and BAC members.

Ratio Decidendi

On the timeliness of the petition: The Court acknowledged that the petition was filed out of time based on the strict application of the 30-day reglementary period for certiorari under Rule 64. However, it relaxed the procedural rules due to the presence of prima facie merit in the case, citing exceptions that allow for the suspension of strict adherence to procedural rules, such as the merits of the case and the potential for reversible errors, even as noted by the OSG. On the right to speedy disposition of cases: The Court found the COA's delay in resolving the case not inordinate, considering the complexity and technical nature of the six disallowances involved. It applied the four-factor test (length of delay, reasons for delay, assertion of the right, and prejudice caused) and concluded that the delay was justified by the necessity for thoroughness in audit, thus not violating the constitutional right. On administrative due process: The Court was unimpressed with the claims of denial of due process. It held that the NDs provided sufficient information regarding the factual and legal bases for the disallowances, allowing parties to formulate defenses. The non-issuance of amended NDs did not impair due process as the assailed Decision provided adequate notification. Furthermore, tribunals are not required to resolve every single argument raised in a motion for reconsideration if they have exhaustively passed upon the decisive issues. On ND No. 2008-06-27-001-101 (2009): The Court affirmed the partial sustainment of the disallowance, holding Shirley R. Baldon liable for P145,770.60 in liquidated damages. It reasoned that the shift from the original ground (unaccomplished deficiency) to the modified ground (liquidated damages for delay) was a residual result of rectification done beyond contract time, a cause subsumed in the original issue. The COA's power to make its own assessment of disallowed disbursements, not limited to the auditor's original grounds, was also cited. On ND No. 2008-06-27-002-101 (2009): The Court sustained the partial lifting of the disallowance related to overpricing due to lack of supporting canvass sheets, as required by COA Memorandum No. 97-012. However, it upheld the remaining disallowance of P1,857,875.33 for overestimation in quantity. The Court found the petitioners' arguments regarding defects in the COA's detailed estimates unmeritorious due to their failure to present the LGU's Program of Work. Regarding equipment rental rates, the Court agreed that DPWH D.O. No. 57, series of 2002, was ineffective due to lack of publication, but found no grave abuse of discretion in COA adopting the DPWH rates as they were lower than the municipal ordinance rates, thus preventing excessive costs. Liability for this disallowance was imposed on BAC Chairman Dino and Municipal Engineer Gonzales, not on Mayor De Castro, citing the Arias doctrine and the technical nature of the documents involved. On ND No. 2008-06-27-003-101 (2009): The Court found merit in the petitioners' arguments and lifted the disallowance of P2,638,776.00. It reasoned that the work suspension order issued by Mayor De Castro, though not explicitly listed under RA 9184's IRR for work suspension, could be justified under the General Welfare Clause of the Local Government Code to protect the municipality's interest during loan negotiations following the failure of bond flotation. The Court also considered the ongoing loan negotiation as a fortuitous event that could excuse the delay. Furthermore, it noted that liquidated damages are triggered by contractor's fault, and the suspension was not due to the contractor's refusal or failure to complete work. The Court also invoked the Madera ruling, stating that no return is required if the ND is set aside, and good faith may excuse return if the suspension was justified. On ND No. 2008-06-27-004-101 (2009): The Court agreed with the OSG that misfeasance is not a ground for disallowance. It found that both the COA RD and COA Proper found insufficient evidence to sustain the original disallowance for alleged delay. The Court's review of the evidence, including accomplishment reports and final payment certifications, preponderantly established that the project was completed within the contract time. Therefore, the amount could not be characterized as an illegal or irregular disbursement. The imposition of liability on Municipal Engineer Gonzales for misfeasance was deemed an administrative liability, not a disallowance, and thus outside COA's power to impose directly as a fine or penalty. On ND Nos. 2008-06-27-005-101 (2009) and 2008-06-27-006-101 (2009): The Court affirmed the lifting of these disallowances for lack of legal basis, acknowledging that the contracts were completed and the public benefited, allowing payment based on quantum meruit. However, it held that the COA's pronouncement of administrative liability for the violation of RA 9184 regarding PhilGEPS use was not an imposition of liability but a preliminary finding for the purpose of initiating appropriate administrative action, which is within COA's authority. The Court deemed it premature to resolve the petitioners' defenses for non-posting at that stage.

Main Doctrine

The Supreme Court affirmed in part and modified in part the COA Decision and Resolution, holding that while some disallowances were lifted due to lack of legal basis or insufficient evidence, others were sustained, and certain officials were held liable for specific violations. The Court also clarified issues related to the application of procurement laws and the extent of COA's audit powers.

Access audio review, related cases, codal links, and more.

Open LexMatePH →