Department of Public Works and Highways v. Italian-Thai Development Public Company

G.R. No. 235853 · 2020-07-13 · J. J.C. REYES, JR., J.: · Primary: Commercial; Secondary: Remedial
REITERATION

Facts

The Antecedents: The Department of Public Works and Highways (DPWH) entered into a Consultancy Agreement with a Joint Venture, including Katahira & Engineers International (KEi), for the design and supervision of road improvement projects. KEi prepared an Engineering Geological and Geohazard Assessment Report (EGGAR) and initially proposed a sloping design. Subsequently, KEi, with DPWH's agreement, developed an "Overhang Design." Italian-Thai Development Public Company, Ltd. (ITD) won the bid for the Suyo-Cervantes Road Section. Several Variation Orders were issued and approved by DPWH, including one standardizing the road width to 6.10 meters with an overhang design and another for the Butac Slope Protection. ITD submitted claims for overrun earthwork quantities due to the overhang design, road realignment, and road improvement. KEi evaluated these claims and recommended denial. ITD then initiated arbitration proceedings with the Construction Industry Arbitration Commission (CIAC). Procedural History: The CIAC rendered a Final Award finding DPWH liable for ITD's claims for overrun earthwork quantities, totaling P106,509,724.49. The CIAC ruled that the change to the overhang design, the instruction to widen the road, and the road improvements led to the overrun earthwork. It also found that ITD's non-compliance with notice requirements was mooted by FIDIC provisions and DPWH's actions, and denied counterclaims. DPWH appealed to the Court of Appeals (CA), which dismissed the appeal, affirming the CIAC's ruling. The CA found that Variation Orders were issued at DPWH's behest, ITD was constrained to realign roads due to these changes, and DPWH and KEi failed to disclose the EGGAR to ITD. The Petition: DPWH seeks the reversal of the CA Decision, alleging grave abuse of discretion by the CA in dismissing its appeal. DPWH argues that the CIAC erred in finding it liable for overrun earthwork quantities due to the overhang design, road realignment, and improvements, and in ruling that FIDIC/COPA provisions on claims were moot. DPWH also questions the CIAC's finding that ITD's varying claims did not cast doubt on its entitlement and that DPWH was not entitled to its cross-claims against KEi. DPWH contends that the CA gravely abused its discretion in appreciating the facts and evidence, warranting a review of factual issues.

Issue(s)

Whether the Supreme Court can review the factual findings of the CIAC and CA. Whether the DPWH is liable for ITD's claims for overrun earthwork quantities due to the overhang design. Whether the DPWH is liable for ITD's claims for overrun earthwork quantities due to road realignment. Whether the DPWH is liable for ITD's claims for overrun earthwork quantities due to road improvements and miscellaneous works. Whether the FIDIC and COPA provisions on the procedure for claims were rendered moot and academic. Whether ITD's varying claims cast doubt on its entitlement. Whether the DPWH is entitled to its cross-claims against KEi. Whether the award of temperate damages to ITD was proper.

Ruling

The Supreme Court denied the Petition for Review and affirmed the Decision of the Court of Appeals. The Court held that the factual findings of the CIAC are generally final and unappealable, and can only be assailed on pure questions of law, or in exceptional cases of grave abuse of discretion, fraud, corruption, misconduct, or exceeding powers. The Court found no such exceptional circumstances in this case, thus upholding the integrity of the arbitration process.

Ratio Decidendi

On the reviewability of CIAC awards: The Court reiterated the principle that arbitral awards from the CIAC are binding and final, except on pure questions of law, as provided by Section 19 of the Construction Industry Arbitration Law. The Court emphasized that it is not a trier of facts and will not review factual findings of arbitral tribunals, even if alleged to be erroneous, unless there is a very clear showing of grave abuse of discretion resulting in lack or loss of jurisdiction, or other exceptional circumstances such as fraud or corruption. The Court found that DPWH's allegation of grave abuse of discretion in the appreciation of facts was insufficient to warrant an exception to the rule. On liability for overrun earthwork quantities due to overhang design: The Court affirmed the findings of the CIAC and CA that DPWH was liable for ITD's claims. The CIAC found that the change from the original sloping design to the overhang design, coupled with KEi's instruction to widen the carriageway and limit the height of stone masonry, constrained ITD to realign the road and excavate into the mountain, leading to overrun earthwork quantities. The CA further noted that DPWH and KEi failed to disclose the EGGAR, which indicated the unsuitability of the rocks for the overhang design, to ITD. These findings, being factual in nature, were given finality. On liability for overrun earthwork quantities due to road realignment: The Court affirmed the findings of the CIAC and CA that DPWH was liable for ITD's claims. The CIAC found that the change from the original sloping design to the overhang design, coupled with KEi's instruction to widen the carriageway and limit the height of stone masonry, constrained ITD to realign the road and excavate into the mountain, leading to overrun earthwork quantities. The CA further noted that DPWH and KEi failed to disclose the EGGAR, which indicated the unsuitability of the rocks for the overhang design, to ITD. These findings, being factual in nature, were given finality. On liability for overrun earthwork quantities due to road improvements and miscellaneous works: The Court affirmed the findings of the CIAC and CA that DPWH was liable for ITD's claims. The CIAC found that the change from the original sloping design to the overhang design, coupled with KEi's instruction to widen the carriageway and limit the height of stone masonry, constrained ITD to realign the road and excavate into the mountain, leading to overrun earthwork quantities. The CA further noted that DPWH and KEi failed to disclose the EGGAR, which indicated the unsuitability of the rocks for the overhang design, to ITD. These findings, being factual in nature, were given finality. On the FIDIC and COPA provisions on claims: The Court agreed with the CIAC and CA that ITD's non-compliance with the notice requirement under the FIDIC and COPA was mooted. The CIAC reasoned that FIDIC allows claims decided under arbitration even without timely notice, and that DPWH's decision to conduct a joint survey estopped it from raising this issue. The CA further found that DPWH effectively waived the requirements by agreeing to direct negotiation and the joint survey. These conclusions were based on factual appreciation and were thus upheld. On ITD's varying claims: The Court found no error in the CIAC's ruling that ITD's varying claims did not cast doubt on its entitlement. The CIAC's determination was based on its evaluation of the evidence presented regarding the overrun earthwork quantities, road realignment, and improvements, which were factual considerations. On DPWH's cross-claims against KEi: The Court affirmed the CIAC's denial of DPWH's cross-claims against KEi. The CIAC found no basis for these claims, and this factual determination was not disturbed by the CA or the Supreme Court. On the award of temperate damages: The Court upheld the CIAC's award of temperate damages to ITD. The CIAC found that while actual damages could not be determined due to an incomplete joint survey, ITD was entitled to temperate damages for the overrun earthwork quantities. This was a factual determination within the CIAC's purview.

Main Doctrine

The factual findings of the Construction Industry Arbitration Commission (CIAC) are generally accorded finality and are not reviewable by the Supreme Court, except on pure questions of law or in cases of grave abuse of discretion resulting in lack or loss of jurisdiction, or when the award was procured by corruption, fraud, or other undue means, or when the arbitrators were guilty of misconduct, or exceeded their powers.

Access audio review, related cases, codal links, and more.

Open LexMatePH →