Movertrade v. Commission on Audit

G.R. No. 214690 · 2021-11-09 · J. INTING, J.: · Primary: Remedial; Secondary: Commercial, Civil
REITERATION

Facts

The Antecedents: Movertrade Corporation (Movertrade) entered into an Agreement with the Department of Public Works and Highways (DPWH) on February 7, 1996, for dredging works in areas affected by the Mount Pinatubo eruptions. The contract amount was P188,698,000.00, which included dredging, distance pumping, and spoil site development. A provision in the agreement stipulated that the contract price would be adjusted on a "No Loss, No Gain" basis if the cost of labor, equipment, materials, and supplies increased due to direct costs from the Government. During project implementation, Movertrade allegedly undertook additional dredging work, claiming it was an extreme measure to counter rapid siltation, resulting in 984,354.26 cubic meters of additional work valued at P43,725,016.23. Procedural History: Movertrade initially sought reimbursement from DPWH for these additional costs, citing the "No Loss, No Gain" provision. After DPWH's failure to pay, Movertrade formally demanded payment in January 2005. An internal DPWH memorandum suggested that while the additional works were not under a valid contract, recovery might be allowed based on quantum meruit, but recommended referral to the Bureau of Construction for factual determination, a recommendation that was not formally approved. Subsequently, Movertrade was advised to file its money claim with the Commission on Audit (COA). Movertrade then filed a petition before the COA Proper seeking payment for the additional dredging works. The COA Proper denied Movertrade's claim, ruling that quantum meruit was inapplicable as a written agreement existed, that Movertrade breached the contract by not obtaining prior approval for the additional works, and that no appropriation existed for these extra expenditures. Movertrade then filed the present petition for Certiorari directly with the Supreme Court, bypassing a motion for reconsideration before the COA. The Petition: Movertrade filed a Petition for Certiorari under Rule 64, in relation to Rule 65, of the Rules of Court, assailing the COA Proper's Decision No. 2014-234. Movertrade argued that the COA acted without or in excess of jurisdiction or with grave abuse of discretion in denying its claim for P43,725,016.23. Movertrade contended that it was entitled to payment on the basis of quantum meruit, asserting that DPWH engineers supervised and expected the additional works, as evidenced by sounding data and as-built plans, and that both DPWH and the public benefited from the project. The petition also sought attorney's fees and legal interest. The respondents, COA and DPWH, argued that the petition was procedurally defective for failing to file a motion for reconsideration before the COA Proper and that quantum meruit did not apply as the additional works were undertaken without DPWH's approval, constituting a breach of contract.

Issue(s)

Whether the petition is procedurally defective for failure to file a Motion for Reconsideration before the COA Proper. Whether Movertrade is entitled to payment for additional dredging works based on the principle of quantum meruit despite the existence of a written contract and lack of prior approval.

Ruling

WHEREFORE, the instant petition is DISMISSED.

Ratio Decidendi

On Issue 1: The Supreme Court held that the petition was procedurally defective because Movertrade failed to move for reconsideration before the COA Proper prior to filing for certiorari. Under Rule 65, certiorari is an extraordinary remedy available only when there is no appeal, nor any plain, speedy, and adequate remedy in the ordinary course of law. A motion for reconsideration is a prerequisite to allow the lower tribunal the opportunity to correct its own errors. This requirement is especially crucial for money claims against the government, as these actions are litigated for the first time before the COA Proper. Movertrade failed to plead any exceptional circumstances that would justify bypassing this mandatory procedural step. On Issue 2: On the substantive merits, the Court ruled that quantum meruit cannot be invoked. The Court emphasized that contracts have the force of law between parties and must be complied with in good faith. Movertrade's Agreement and Bid Book explicitly stated that any work performed in excess of specifications without a DPWH order would not be paid for. By proceeding without prior approval, Movertrade committed a breach of contract. Citing Movertrade Corp. v. COA (2015) and MMDA v. D.M. Consunji, Inc., the Court reiterated that a contractor bound by a written agreement who breaches its terms cannot recover via quantum meruit. Furthermore, the lack of an appropriation for the additional works violated Section 85 of P.D. No. 1445, rendering the claim legally unsustainable.

Main Doctrine

The principle of quantum meruit, which allows for payment based on the value of services rendered in the absence of a contract, is inapplicable when a written agreement exists and the claimant has breached its specific provisions. In government contracts, strict adherence to the 'plans and specifications' and the requirement for 'prior approval' for additional works are mandatory. Furthermore, procedural due process requires the filing of a Motion for Reconsideration before the Commission on Audit (COA) Proper as a condition precedent to a petition for certiorari, as money claims are litigated for the first time before the COA Proper.

Access audio review, related cases, codal links, and more.

Open LexMatePH →