Cruz v. Commission on Audit

G.R. No. 246777 · 2021-03-02 · J. DELOS SANTOS, J.: · Primary: Taxation; Secondary: Administrative Law
REITERATION

Facts

The Antecedents: Sto. Cristo Construction (petitioner) was awarded government contracts for road rehabilitation and improvement in Mexico, Pampanga, in 2010. Following the completion of these projects, a reassessment by the Quality Assurance Unit (QAU) of the Department of Public Works and Highways (DPWH) revealed adverse findings. Subsequently, COA Technical Inspectors conducted an inspection which indicated an overstatement of embankment materials. This led to the issuance of four notices of disallowance by the Audit Team Leader (ATL), disapproving payments totaling P22,626,714.71 for ten projects. Specifically, Notice of Disallowance (ND) No. 11-001-101-09/10 disallowed P14,926,319.76, representing deficiencies from overestimates in embankment materials. Procedural History: The DPWH officials and personnel initially appealed the disallowance, arguing that the projects were pre-audited, that erosion affected the projects, and that the disallowance was moot as the projects were already paid. Subsequently, Noel J. Cruz, proprietor of Sto. Cristo Construction, requested corrective measures and mint surveys for the projects. The COA Regional Office No. III, in Decision No. 2013-41, affirmed the notices of disallowance. Petitioner then filed an appeal, claiming lack of personal receipt of the ND and asserting that rectification works were completed under DPWH supervision. The COA Proper, in Decision No. 2015-11, declared the disallowances final and executory. A motion for reconsideration was denied by the COA in Decision No. 2018-317, which is now under review. The Petition: This case is a Petition for Certiorari under Rule 64 in relation to Rule 65 of the Rules of Court, assailing COA Decision No. 2018-317. Petitioner argues that the COA committed grave abuse of discretion by failing to appreciate the rectification works undertaken, violating its right to due process by rendering a decision without proper basis, and erroneously relying on the presumption of regularity. Petitioner contends that the DPWH requested and found the rectification works sufficient. The COA, however, maintains that there was no showing that the rectifications were confirmed as compliant with COA reevaluation and that the DPWH officials did not invoke these works as defenses in their appeal. The core issue is whether the COA committed grave abuse of discretion in sustaining the disallowance despite the alleged rectification works.

Issue(s)

Whether the Commission on Audit (COA) committed grave abuse of discretion amounting to lack or excess of jurisdiction when it sustained the disallowance of the amount paid to the contractor despite the rectification works undertaken by the latter. Whether petitioner's right to due process was violated.

Ruling

The Supreme Court DISMISSED the Petition for Certiorari and AFFIRMED the Commission on Audit Decision No. 2018-317 dated March 15, 2018.

Ratio Decidendi

On the issue of grave abuse of discretion and rectification works: The Court held that the COA did not commit grave abuse of discretion. The disallowance was based on the "overestimation of embankment materials in the Program of Work," which stemmed from deficiencies in the detailed engineering phase, not from defects in the petitioner's actual performance. The audit team explicitly stated that overestimation would not have occurred with complete detailed engineering. The Court emphasized that the issue was the excessive use of public funds due to overestimation, which requires the return of the excess payment, not the rectification of the work itself. The rectification works, even if undertaken, did not address the core issue of overpayment caused by inaccurate initial estimates. The Court noted that if the rectifications were indeed sufficient, the DPWH officials should have invoked them as defenses in their appeal. The findings of the DPWH-QAU and COA Technical Inspectors, who are presumed to have acted regularly in the performance of their duties, reinforced the disallowance. The Court reiterated that public officials are entitled to the presumption of good faith and regularity in the performance of their duties. The COA's reliance on this presumption was justified because the ND obligated the return of overestimates, not just rectification of work. Furthermore, there was no evidence of irregularity in the performance of the DPWH-QAU and COA Technical Inspectors, whose uniform factual findings were not disturbed. The Court affirmed the COA's role as the guardian of public funds and its wide latitude in exercising its constitutional duty, sustaining its findings when supported by substantial evidence, which was the case here. On the issue of due process: The Court found no violation of petitioner's right to due process. While petitioner claimed late receipt of the ND, the records did not show the exact date of receipt, making it difficult to determine if the appeal was timely filed. Despite this, the COA accommodated the appeal, allowed petitioner to present its side, and decided the case on the merits. The Court also pointed out that petitioner filed an appeal memorandum instead of a petition for review before the Commission Secretariat, which was a procedural misstep. Therefore, petitioner could not justifiably claim denial of due process.

Main Doctrine

Rectification works undertaken by a contractor do not automatically negate a notice of disallowance for overpayment due to overestimation of materials in the Program of Work, especially when the overestimation stemmed from deficiencies in the detailed engineering phase and not from defects in the actual performance of the work. The recovery of excess payments made to the contractor is the primary concern in such cases.

Access audio review, related cases, codal links, and more.

Open LexMatePH →