Yu v. Heirs of Sia

G.R. No. 248495 · 2022-07-06 · J. ZALAMEDA, J.: · Primary: Civil; Secondary: Remedial
REITERATION

Facts

The Antecedents: Engr. Ruben Y. Yu, doing business as Ryu Construction, entered into a contract with the Heirs of Manuel Sia, represented by Rosemarie H. Sia, for the construction of a four-story commercial building for P9,842,240.00. Ryu Construction received an advance payment of P3,000,000.00, with the remainder to be paid through progress billings. Upon completion in 2003, Ryu Construction demanded the remaining balance of P448,240.00. The Heirs of Sia refused payment, citing the non-issuance of an occupancy permit and defects in the third and fourth floors, specifically undersized rooms violating Presidential Decree No. 1096 (National Building Code). Procedural History: Ryu Construction filed a collection case against the Heirs of Sia. The Regional Trial Court (RTC) ruled in favor of Ryu Construction, ordering the payment of the remaining balance, attorney's fees, and costs, finding that the contractor had complied with the contract and that the defects were not attributable to him. On appeal, the Court of Appeals (CA) reversed the RTC's decision, setting aside the judgment and ordering Ryu Construction to reimburse the Heirs of Sia for renovation costs, plus moral and exemplary damages, attorney's fees, and costs. The CA found that the non-issuance of the occupancy permit was due to Ryu Construction's failure to comply with PD 1096 and that the owner was justified in undertaking renovations. The Petition: Engr. Ruben Y. Yu filed a Petition for Review on Certiorari under Rule 45 of the Rules of Court, assailing the CA's decision. The petition argues that the CA erred in reversing the RTC's findings and in holding that the defects were the fault of the petitioner. The core of the petition is that the CA's factual findings were contrary to those of the trial court, presenting an exception to the general rule that questions of fact are not reviewable under Rule 45. The Supreme Court, however, found both parties to be in pari delicto due to their mutual violation of PD 1096, leading to the dismissal of both the complaint and the counterclaim.

Issue(s)

Whether the Court of Appeals erred in reversing the Regional Trial Court's decision and whether the petitioner is entitled to the remaining balance of the contract price. Whether the respondents are entitled to reimbursement for renovation costs and damages.

Ruling

The Supreme Court denied the petition, reversed and set aside the decision of the Court of Appeals, and dismissed both the complaint of Ruben Yu and the counterclaim of Rosemarie Sia. The Court found that both parties were in pari delicto, rendering their contract void and unenforceable.

Ratio Decidendi

On the issue of whether the Court of Appeals erred in reversing the Regional Trial Court's decision and the petitioner's entitlement to the remaining balance: The Court found that both parties were in pari delicto as they entered into a contract for the construction of a building that violated PD 1096. The construction contract required adherence to plans and specifications, and the owner's payment was conditioned on the occupancy permit. However, both parties, through their actions and knowledge, contributed to the illegality of the contract. The petitioner, as a licensed contractor, was expected to know and follow PD 1096, and was informed of the defects by the architect. The owner, Rosemarie Sia, also had a responsibility to ensure compliance with PD 1096, and her claim of being a layperson did not excuse her from this duty. The violation was present in the approved building plan itself, indicating a mutual understanding or at least a failure to exercise due diligence by both parties. Therefore, neither party could seek affirmative relief from the courts based on this illegal contract. On the issue of whether the respondents are entitled to reimbursement for renovation costs and damages: Since the Court found the contract to be void due to the parties being in pari delicto, neither party could claim affirmative relief. Article 1411 of the Civil Code states that when the nullity of a contract proceeds from the illegality of the cause or object, and the act constitutes a criminal offense, both parties being in pari delicto shall have no action against each other. The construction of a building in violation of PD 1096 is an illegal act. Consequently, the claims for reimbursement of renovation costs and damages by the respondents, as well as the claim for the remaining balance by the petitioner, were dismissed. The Court noted that while Rosemarie Sia incurred renovation costs, her own participation in the illegal contract precluded her from recovering these expenses from the petitioner. Similarly, the petitioner could not recover the unpaid balance for work done under an illegal agreement. The Court's decision to dismiss both the complaint and counterclaim underscores the principle that courts will not lend their aid to enforce or recover under illegal contracts where both parties are equally at fault.

Main Doctrine

When both parties to a construction contract are found to be in pari delicto for entering into an agreement that violates mandatory building regulations, neither party may seek affirmative relief from the courts, and their claims against each other are dismissed.

Access audio review, related cases, codal links, and more.

Open LexMatePH →