Hyundai Engineering Co. v. National Grid Corporation

G.R. No. 214743 and G.R. No. 248753 · 2023-12-04 · J. SINGH, J.: · Primary: Commercial; Secondary: Remedial
REITERATION

Facts

The Antecedents: The Consortium of Hyundai Engineering Co., Ltd. and Hyundai Corporation (Hyundai) entered into a Construction Contract with the National Transmission Corporation (TransCo) for the Maramag-Bunawan Transmission Backbone Project. Subsequently, TransCo and the Power Sector Assets and Liabilities Management Corporation (PSALM) entered into a Concession Agreement with the National Grid Corporation of the Philippines (NGCP), wherein NGCP took over TransCo's transmission business. A Construction Management Agreement (CMA) was also executed between NGCP, TransCo, and PSALM. TransCo sent a letter to Hyundai requesting confirmation for the transfer/assignment of contracts, including the Construction Contract, to NGCP. Hyundai did not respond, which was deemed consent. Hyundai subsequently dealt with NGCP for contract implementation. A dispute arose when NGCP sought to charge Hyundai liquidated damages for project delays. Hyundai initiated arbitration proceedings before the Construction Industry Arbitration Commission (CIAC) against both NGCP and TransCo. Procedural History: The CIAC initially denied the motions to dismiss filed by TransCo and NGCP. However, the Court of Appeals (CA) reversed this, ruling that NGCP was not bound by the arbitration clause as it was not a party to the Construction Contract and was merely a Construction Manager, not an assignee. The CA also found that the arbitration between Hyundai and TransCo would be ineffectual without NGCP. Subsequently, the CIAC dismissed Hyundai's Request for Arbitration without prejudice. Hyundai appealed this dismissal to the CA, which affirmed the dismissal. Hyundai then filed petitions before the Supreme Court. The Petition: Hyundai filed two consolidated petitions for review, assailing the CA's decisions that denied Hyundai's claims against NGCP and TransCo before the CIAC, and the CIAC's dismissal of the arbitration proceedings.

Issue(s)

Whether the CIAC has jurisdiction over the dispute involving Hyundai, TransCo, and NGCP. Whether the CIAC Tribunal correctly dismissed the Request for Arbitration.

Ruling

The Supreme Court granted both consolidated petitions, reversed the Court of Appeals' decisions, and affirmed the CIAC Resolution denying the motions to dismiss. The Court directed the CIAC to proceed with the resolution of the dispute with dispatch.

Ratio Decidendi

On the CIAC's Jurisdiction: The Court held that the CIAC has jurisdiction over the dispute. Citing Executive Order No. 1008 and Section 35 of Republic Act No. 9285, the CIAC's jurisdiction extends to disputes arising from or connected with construction contracts where parties are bound by an arbitration agreement, directly or by reference. The Court found that NGCP, through the Concession Agreement and the CMA, effectively became TransCo's assignee of the Construction Contract. The Concession Agreement stipulated that NGCP would exercise all of TransCo's rights and discharge all of its obligations under transferred contracts. The Court emphasized that NGCP's role as Construction Manager, as defined in the CMA, did not negate its assumption of TransCo's contractual obligations, including the arbitration clause. The Court applied the principle of relativity of contracts (Article 1311 of the Civil Code), stating that NGCP, as an assignee, is bound by the terms of the Construction Contract. Furthermore, Section 35 of R.A. No. 9285 explicitly includes project managers as parties who can be bound by arbitration agreements in construction disputes, preventing the splitting of cases and promoting efficient dispute resolution. The Court concluded that NGCP's contractual duty to recognize the arbitration clause arose from the Concession Agreement and the CMA, which obligated it to act consistently with TransCo's obligations under the Construction Contract. On the CIAC Tribunal's Dismissal of the Case: The Court ruled that the CIAC Tribunal should not have dismissed the case. Since the CIAC was found to have jurisdiction over all parties, including NGCP, the grounds for dismissal were rendered invalid. The Court found that Hyundai's claims against TransCo, arising from events prior to NGCP's assumption of business, were still valid and should be determined by the CIAC, as TransCo retained certain liabilities under Section 5.08 of the Concession Agreement. The Court also reiterated that the CA's prior ruling on jurisdiction was reversed, making the CIAC's dismissal based on that ruling erroneous. Therefore, the CIAC Award and the Second CA Decision were reversed, and the CIAC was directed to proceed with resolving the dispute.

Main Doctrine

The National Grid Corporation of the Philippines (NGCP), as assignee of TransCo's rights and obligations under a construction contract, is bound by the arbitration clause within that contract, even if it was not an original signatory, and thus falls within the jurisdiction of the Construction Industry Arbitration Commission (CIAC).

Access audio review, related cases, codal links, and more.

Open LexMatePH →