Blossom & Co. v. Manila Gas Corporation

G.R. No. 32958 · 1930-11-08 · J. JOHNS, J.: · Primary: Commercial; Secondary: Civil
REITERATION

Facts

1. The Antecedents: Blossom and Company, Inc. (plaintiff) entered into a contract with Manila Gas Corporation (defendant) for the sale and delivery of water gas tar and coal gas tar over a period of years. The contract stipulated monthly quantities, prices, and conditions for price adjustments based on the cost of raw materials. The contract was later amended to extend its duration and modify the quantities and plaintiff's options regarding purchase volumes, including the right to take up to 50% or the entire output of coal gas tar and up to the entire output of water gas tar under certain conditions and notice periods. The plaintiff also purchased land from the defendant, executing a mortgage to secure the balance of the purchase price. 2. Procedural History: The plaintiff alleges the defendant breached the contract in July 1920 by ceasing deliveries due to increased prices. The plaintiff filed a lawsuit (Case No. 25352) in the Court of First Instance of Manila, seeking damages and specific performance. The lower court awarded damages of P26,119.08 for the breach from July 1920 to September 1923 but refused specific performance, leaving the plaintiff to seek damages for subsequent breaches. This judgment was affirmed by the Supreme Court. Subsequently, the defendant initiated a foreclosure action against the plaintiff for the unpaid balance on the land purchase. The plaintiff alleges the defendant overcharged for tars delivered after March 26, 1926, and refused to provide cost information for raw materials, despite the contract's price adjustment clause. The plaintiff also alleges the defendant refused to honor its contractual options to take larger quantities of tar. The plaintiff filed the current action seeking rescission of the contract and damages for breaches occurring after September 1923. The trial court, after a referee's report, found the plea of res judicata to be sustained, limiting damages to P2,219.60 for overcharges on deliveries made after April 1926. 3. The Petition: The plaintiff appealed the trial court's decision, arguing that the prior judgment for damages up to September 1923 was not res judicata for subsequent breaches of the continuing contract. The plaintiff contended that the trial court erred in holding that the defendant's initial repudiation constituted an election to dissolve the contract, estopping the plaintiff from claiming the contract remained alive. The appeal also challenged the trial court's interpretation of the contract's quantity options and its findings regarding the plaintiff's use of these options and the defendant's liability for refusing deliveries. The plaintiff sought to recover damages for breaches occurring after September 1923, arguing that the contract was a continuing one and that the prior judgment only covered damages up to a specific date, not barring subsequent claims for later breaches.

Issue(s)

Whether the prior judgment awarding damages for breach of contract from July 1920 to September 1923 bars the present action for damages arising from subsequent breaches of the same contract. Whether the plaintiff's election to sue for damages in the first action constituted a waiver of the right to claim specific performance or to keep the contract alive for future breaches. Whether the trial court erred in holding that the plaintiff's demands for additional tars were extravagant and not made in good faith, leading to the plaintiff's blame for the failure of performance. Whether the trial court erred in awarding damages only in the sum of P2,219.60 for overcharges on deliveries after April 1926, instead of the P319,253.40 claimed by the plaintiff.

Ruling

The Supreme Court affirmed the decision of the lower court, holding that the plea of res judicata must be sustained. The Court ruled that the prior judgment awarding damages for the breach of the contract from July 1920 to September 1923 was a bar to the present action for damages arising from subsequent breaches of the same contract. The Court found that the plaintiff, by suing for damages for a total breach of the contract, had elected to treat the contract as rescinded and could not split its cause of action. The Court also found that the deliveries made after April 1926 were not under the original contract and that the plaintiff was only entitled to recover for overcharges on those specific deliveries.

Ratio Decidendi

On the issue of res judicata and the splitting of causes of action: The Court held that the prior judgment awarding damages for breach of contract from July 1920 to September 1923 was a bar to the present action for damages arising from subsequent breaches of the same contract. The Court cited authorities stating that a contract to do several things at several times is of a nature to authorize successive actions, but where the covenant or contract is entire and the breach total, there can be only one action, and the plaintiff must therein recover all his damages. In this case, the plaintiff's original complaint alleged a willful and deliberate breach and a flat refusal to make any deliveries since July 1920, which constituted a total breach of the entire contract. By recovering damages for this total breach, the plaintiff elected to treat the contract as rescinded and could not split its demand by bringing successive actions for subsequent breaches. The Court emphasized that the plaintiff, in its former action, had prayed for damages and specific performance, but the court refused specific performance and left the plaintiff with its remedy for damages for subsequent breaches. However, the Supreme Court clarified that when the contract is entirely breached, the plaintiff must recover all damages in one suit. The Court noted that the plaintiff's original complaint alleged a continuous refusal to deliver since July 1920, which was a total breach, and therefore, all damages, past and prospective, should have been claimed in that first action. The Court concluded that the plaintiff could not split its cause of action and that the prior judgment was conclusive as to all claims arising out of the entire contract. On the plaintiff's election of remedies: The Court found that by suing for damages for the breach of contract and recovering a judgment, the plaintiff had elected to treat the contract as rescinded. The Court cited authorities stating that upon refusal by the seller, after partial performance, to longer comply with his contract to sell and deliver goods in installments, the buyer cannot keep the contract in force and maintain actions for breaches as they occur but must recover all his damages in one suit. The Court reasoned that the plaintiff's original complaint alleged a total breach and a refusal to carry out the terms of the contract, and by seeking damages for this breach, the plaintiff implicitly affirmed the termination of the contract. Therefore, the plaintiff was estopped from claiming that the contract was still alive when that suit was brought and could not maintain successive actions for subsequent breaches. On the plaintiff's demands for additional tars and good faith: The Court implicitly agreed with the trial court's finding that the plaintiff's demands for additional tars were extravagant and not made in good faith, which contributed to the failure of performance. While not explicitly detailed in the Supreme Court's final ruling, the trial court's decision, which the Supreme Court affirmed on the issue of res judicata, indicated that the plaintiff's actions in demanding maximum quantities of coal tar and minimum of water gas tar, with reservations, announced an intention to breach the contract, and thus the defendant was under no obligation to deliver maximum quantities. The Court's affirmation of the trial court's decision on the res judicata issue meant that the subsequent breaches and the plaintiff's claims for damages related to them were already adjudicated or should have been adjudicated in the first case. On the award of damages for overcharges: The Court affirmed the trial court's award of P2,219.60 for overcharges on deliveries made after April 1926. The Court agreed with the referee and the trial court that the charges for deliveries during 1926 were too high, as the price was to be fixed on the basis of raw materials. The Court found this charge to be meritorious and adopted the referee's findings and calculations for this specific amount. This ruling was based on the finding that the defendant broke its contract for the sale and delivery of tars on and after April 1926, and the plaintiff was entitled to recover for these specific overcharges, separate from the res judicata issue concerning the earlier breaches.

Main Doctrine

A judgment recovered for a single breach of a continuing contract, where the breach is total, is a bar to a subsequent suit for subsequent breaches of the same contract, as all damages must be recovered in one action.

Access audio review, related cases, codal links, and more.

Open LexMatePH →