Philrock v. Cid

G.R. Nos. 132848-49 · 2001-06-26 · J. PANGANIBAN, J.: · Remedial Law
REITERATION

Facts

The Antecedents: Spouses Vicente and Nelia Cid engaged Philrock, Inc. to supply ready-mix concrete for the construction of their residence, entering into transactions where Philrock billed P125,586.25 via its Marketing Department but charged only P102,586.25 at the Batching Plant, creating an excess payment issue of P23,276.25. On various delivery dates, Philrock's transit mixers supplied concrete that arrived at the jobsite partially unworkable, requiring addition of water and manual pushing, leading to defects like cracks and honeycombs in poured structures due to improper mix proportions upon arrival. The Cids halted construction, incurred retrofitting costs of P65,000, wasted P13,404.54 worth of unworkable concrete, and suffered family dislocation—Nelia in a dingy bodega, son in makeshift room, daughter with aunt until marriage—with Vicente dying without seeing the home completed. Philrock officers assured refunds and fixes in staff meetings and visits on July 31, 1992, but issues persisted, prompting the Cids' demands for refunds, repairs, and damages. No evidence showed all mixers arrived within allowable time for workability, and defects logically traced to unworkable pours despite correct plant mix. Procedural History: On September 14, 1992, Cids filed damages complaint against Philrock and seven officers/engineers in RTC Quezon City Branch 82; on December 7, 1993, RTC dismissed and referred to CIAC upon parties' November 24, 1993 Agreement to Arbitrate signed by Philrock's president Perry Y. Uy and Atty. Ismael J. Andres, and Cids' Nelia G. Cid and Atty. Esteban A. Bautista. Preliminary conferences deadlocked on including moral/exemplary damages, tort, and non-signatory officers; both parties requested remand on April 2, 1994; CIAC ordered dismissal for referral to RTC on April 13, 1994. Cids moved RTC to set for hearing (opposed by Philrock); RTC remanded to CIAC on June 13, 1995, declaring no jurisdiction. CIAC resumed; Philrock sought suspension arguing RTC mistake on remand basis, but Cids agreed to exclude officers; parties signed Terms of Reference August 21, 1995, affirming arbitration. Philrock's Motion to Dismiss denied September 22, 1995; CIAC directed hearings and fee payment February 7, 1996; CIAC awarded Cids P23,276.25 excess +6% interest, P65,000 retrofitting, P13,404.54 wasted concrete, P50,000 moral, P50,000 nominal, P50,000 attorney's fees/expenses, P144,756.80 arbitration fees minus payments on September 24, 1996. Philrock filed certiorari (CA-GR SP 39781) and review (CA-GR SP 42443); CA consolidated, denied July 9, 1997, affirmed CIAC, denied MR February 24, 1998. The Petition: Philrock petitioned Supreme Court under Rule 45, arguing: (A) CIAC lost jurisdiction post-dismissal/withdrawal; (B) no cause of action due to Cids' negligence under National Building Code Sec. 308 lacking supervisor; (C-G) awards improper—excess payment unraised/unjustified, no interest liability (tendered check refused), retrofitting/wasted concrete Cids' fault, no moral/nominal damages/bad faith, no attorney's fees (self-represented), no arbitration fees liability.

Issue(s)

Whether CIAC retained jurisdiction after dismissal/referral and parties' participation. Whether Cids had cause of action against Philrock. Whether CIAC monetary awards (excess payment + interest, retrofitting, wasted concrete, moral/nominal damages, attorney's fees, arbitration fees) were proper.

Ruling

Petition denied; CA Decision affirmed, but nominal damages award deleted for lack of basis as actual damages proven; costs against petitioner.

Ratio Decidendi

On Issue 1 (Jurisdiction): Section 4, EO 1008 vests CIAC original/exclusive jurisdiction over construction disputes upon voluntary arbitration agreement, persisting until full termination despite April 13, 1994 referral order, as no intent to end case and CIAC Rules Sec. 3 disregard technicalities. Parties' November 24, 1993 Agreement validly conferred jurisdiction; Cids removed impasse by excluding non-signatories; Philrock actively participated post-referral, signing August 21, 1995 Terms of Reference affirming 'differences be settled by Arbitral Tribunal,' estopping challenge per policy against subverting arbitration (Spouses Benitez v. CA). Philrock's remand arguments conceded RTC no jurisdiction, reinforcing CIAC authority; post-adverse decision assaults rejected. CIAC factual findings final per EO 1008 Sec. 19, reviewable only on law. On Issue 2 (Cause of Action): Defined as act/omission violating plaintiff's right (Camara v. CA; Delos Reyes v. CA), here Cids' right to quality concrete per purchase, Philrock's obligation to deliver workable mix, breached by substandard arrival causing defects—CIAC found plant mix correct but delays/unworkability proven, defects from poured unworkable concrete. Cids disproved negligence; damages flowed from Philrock's breach, not Code violation. On Issue 3 (Monetary Awards): Factual awards final if substantial evidence (Villaflor v. CA), reviewable for grave abuse; excess P23,276.25 raised in Terms of Reference para. 9 and hearings, per Civil Code Art. 2209 6% interest from delay (Sept. 26, 1995). Retrofitting P65,000, wasted concrete P13,404.54 actual damages from breach; moral P50,000 proper for family agony (7+ years delay, separation, Vicente's death); nominal deleted as actual proven (Go v. IAC); attorney's fees/expenses P50,000 valid despite pro se, covering litigation costs in bad faith refusal context; arbitration fees P144,756.80 proper liability.

Main Doctrine

Under Section 4 of Executive Order No. 1008, the Construction Industry Arbitration Commission (CIAC) has original and exclusive jurisdiction over disputes arising from or connected with construction contracts in the Philippines, provided the parties agree to submit to voluntary arbitration, encompassing issues like materials defects, damages, and delays. Once jurisdiction is acquired through an Agreement to Arbitrate, it remains until full termination of the case, unaffected by interim orders like dismissals for referral back to courts, as technical rules do not strictly apply per CIAC Rules. Parties who actively participate in arbitration proceedings, such as signing Terms of Reference after initial disputes, are estopped from later challenging CIAC jurisdiction, preventing subversion of arbitration objectives. Factual findings and monetary awards by CIAC, supported by substantial evidence, are final and unappealable except on pure questions of law appealable to the Supreme Court, according quasi-judicial bodies great respect in their expertise. Cause of action in contract breaches requires proof of plaintiff's right, defendant's obligation, and violative act/omission, as in substandard concrete delivery causing structural defects. Moral damages are awardable for unwarranted sufferings from breach, but nominal damages are improper where actual damages are compensated.

Access audio review, related cases, codal links, and more.

Open LexMatePH →