Chua v. Colorite Marketing

G.R. Nos. 193969-193970 & 194027-194028 · 2017-07-05 · J. REYES, J.: · Primary: Civil; Secondary: Remedial
CLARIFICATION

Facts

The Antecedents: On November 15, 2003, Colorite Marketing Corporation (Colorite) entered into a construction contract with Architect Ka Kuen Chua (KKCA) for a four-storey building in Makati City for a price of Php33,000,000.00, to be completed within 365 days. The contract stipulated liquidated damages of Php10,000.00 for each day of delay. An addendum to the contract made KKCA responsible for all excavation and soil protection works. During excavation works performed by a subcontractor under KKCA's supervision, soil erosion occurred on January 17, 2004, damaging the adjacent property of the Hontiveros family. This led to the issuance of a Hold Order by the Makati City Building Official, halting all construction activities. Procedural History: Due to the prolonged delay, Colorite filed a claim with the Construction Industry Arbitration Commission (CIAC) for liquidated damages and loss of rental income. KKCA counterclaimed for costs of soil protection, restoration, and design fees, arguing the delay was due to the Hold Order and Colorite's failure to pay its alleged share of restoration costs. The CIAC found both parties equally responsible for the delay and awarded Colorite only 50% of its claimed liquidated damages. Both parties appealed to the Court of Appeals (CA), which affirmed the CIAC's decision with modifications, finding that Colorite contributed to the delay by failing to pay a promised Php700,000.00 for restoration costs. The Petition: Both parties filed petitions for review on certiorari under Rule 45 before the Supreme Court. Colorite argued it was entitled to full liquidated damages and was not liable for any restoration or maintenance costs. KKCA contended it was not at fault for the erosion, should not be liable for any liquidated damages, and should be released from its obligation to finish the project due to strained relations and the delay rendering performance extremely difficult.

Issue(s)

Whether KKCA was solely at fault for the erosion that caused the project delay. Whether a subsequent agreement existed for Colorite to share in the restoration costs of the damaged adjacent property. Whether Colorite is entitled to full liquidated damages for the entire period of delay. Whether KKCA is obligated to finish the construction project. How the increase in construction costs due to the prolonged delay should be apportioned between the parties.

Ruling

The petitions are partially granted. The Decision of the Court of Appeals dated July 28, 2009, and its Resolution dated October 4, 2010, are AFFIRMED with MODIFICATIONS. The Court found KKCA negligent for the erosion but held Colorite equally at fault for the protracted delay. Liquidated damages for Colorite were equitably reduced to Php4,210,000.00. KKCA was ordered to finish the project, with the increased construction costs to be shared: 60% by KKCA and 40% by Colorite.

Ratio Decidendi

On Issue 1 (Fault for Erosion): Yes, the Supreme Court held that KKCA was at fault for the erosion. The contract's Addendum #01 explicitly placed all excavation and soil protection works under KKCA's scope of work and supervision. Evidence, including testimony from KKCA's own consultant, established that KKCA failed to install necessary soil protection measures before the excavation caused the erosion; it only implemented remedial measures after the damage had occurred. This failure to take preventive measures constituted negligence and was the proximate cause of the damage that led to the Hold Order and the initial project delay. On Issue 2 (Restoration Cost Agreement): No, the Court found that no perfected subsequent agreement existed for Colorite to share in the restoration costs. While KKCA alleged a 70-30 sharing agreement, the evidence was insufficient and self-serving. The CA's finding of an agreement for a fixed Php700,000.00 was also unsupported, as there was no clear meeting of the minds on this essential term. Applying the principle that a contract is perfected only when parties agree on every point, the Court concluded that the original contract's provision (Article XIII), which held KKCA solely liable for damages to third parties, remained in full force and effect. On Issue 3 (Liquidated Damages): No, Colorite is not entitled to full liquidated damages. While KKCA's negligence caused the initial delay, Colorite was also at fault for the protracted delay. Under Article 2203 of the Civil Code, an injured party has a duty to exercise the diligence of a good father of a family to minimize damages. Colorite had a contractual right to terminate the contract and take over the project when the delay exceeded the allowable slippage but failed to do so. Its inaction, which allowed the delay to extend for years, was a breach of its duty to mitigate losses. Therefore, the Court, pursuant to Articles 2227 and 1229 of the Civil Code, equitably reduced the liquidated damages, limiting the award to the period from the original completion date until a reasonable time after the adjacent property was restored (a total of 421 days). On Issue 4 (Obligation to Finish Project): Yes, KKCA is obligated to finish the project. The construction contract remained subsisting as neither party had rescinded it. The Court rejected KKCA's arguments of 'strained relations' and 'involuntary servitude.' These doctrines are inapplicable to a contract for a piece of work, which is governed by the principle of the obligatory force of contracts. To release KKCA from its freely assumed obligation would violate this fundamental principle. If KKCA believed it had grounds to be released, it should have filed an action for rescission. On Issue 5 (Apportionment of Increased Costs): The increased construction costs must be shared by both parties. The increase in cost over and above the contract price is a form of actual damages resulting from KKCA's breach. However, since Colorite's inaction also contributed significantly to the prolonged delay during which costs escalated, it would be unjust enrichment to charge the entire amount to KKCA. The Court found it equitable to apportion the liability for the increased costs, with KKCA shouldering 60% and Colorite shouldering 40%, reflecting their respective degrees of fault in the protracted delay.

Main Doctrine

In a construction contract, while a contractor's negligence may be the proximate cause of an initial project delay, the project owner also has a duty under Article 2203 of the Civil Code to exercise the diligence of a good father of a family to minimize resulting damages. If the owner has a contractual right to terminate the contract and take over the project but fails to do so, allowing the delay to become protracted, the owner is considered equally at fault. This mutual fault justifies the equitable reduction of liquidated damages and the apportionment of increased construction costs between both parties.

Access audio review, related cases, codal links, and more.

Open LexMatePH →