Encarnacion Construction & Industrial Corp. v. Phoenix Ready Mix Concrete Development & Construction, Inc.

G.R. No. 225402 · 2017-09-04 · J. PERLAS-BERNABE, J.: · Civil Law
REITERATION

Facts

The Antecedents: On January 27, 2009 and March 25, 2009, respondent Phoenix Ready Mix Concrete Development and Construction, Inc. (Phoenix) entered into two separate Contract Proposals and Agreements with petitioner Encarnacion Construction & Industrial Corporation (ECIC) for the supply and delivery of specified quantities of ready-mix concrete with agreed strengths of 3000 and 3500 psi G-3/4 7D PCD, intended for the construction of the Valenzuela National High School (VNHS) Marulas Building, specifically the 3rd floor slab. ECIC duly received the deliveries between these dates and up to April 29, 2009, as evidenced by delivery receipts, but refused payment despite Phoenix's written demands starting November 5, 2009, claiming the concrete was substandard. ECIC alleged that samples from the 3rd floor slab failed to achieve the required comprehensive strength of 6,015 psi even after 100 days, leading the City Engineer's Office of Valenzuela to inspect, note hairline cracks via letters dated May 20 and May 29, 2009, and order demolition and reconstruction, incurring ECIC additional costs of P3,858,587.84. Phoenix clarified that 'concrete' (mixture of cement, gravel, sand, etc.) differed from 'cement,' and Paragraph 15 of the Agreements mandated claims on quality, strength, or quantity at delivery time, with failure constituting waiver releasing Phoenix from liability. Prior to these, ECIC and Phoenix had three similar agreements on November 6, 2008, February 18, 2009, and February 27, 2009, under identical terms, indicating ECIC's familiarity. ECIC notified Phoenix of the defects only on June 11, 2009, 48 days post-last delivery and after City Engineer's notices. Procedural History: Phoenix filed a Complaint for Sum of Money on January 25, 2010 before RTC Imus, Cavite Branch 20 (Civil Case No. 3547-10), seeking P982,240.35 plus interest and attorney's fees. ECIC answered with counterclaim on June 16, 2010, seeking damages but initially failed to pay docket fees until June 18, 2010. RTC Decision dated December 4, 2013 granted Phoenix P865,410.00 at 12% interest from November 5, 2009, P50,000 attorney's fees, and costs, holding ECIC waived claims via estoppel for delayed objection, breached by non-payment, and dismissed counterclaim for late fees. ECIC appealed to CA (CA-G.R. CV No. 102671), arguing timely fees and substandard concrete. CA Decision July 22, 2015 affirmed, accepting fee payment as timely but upholding waiver under Paragraph 15, rejecting adhesion contract invalidity absent disadvantage proof; MR denied June 29, 2016. The Petition: ECIC petitioned for review on certiorari under Rule 45, insisting Paragraph 15 void as adhesion contract, substandard concrete proven by tests (Philippine Geoanalytics showing strength failure) and City orders causing reconstruction costs, non-waiver due to no signature on reverse page, and improper RTC/CA factual findings on causation, urging counterclaim allowance.

Issue(s)

Whether the Court of Appeals erred in upholding the validity of Paragraph 15 of the Agreement as a contract of adhesion and in finding waiver of ECIC's claims on the substandard quality of the delivered ready-mix concrete. Whether the Court of Appeals erred in denying ECIC's counterclaim for damages despite evidence of defects and causation.

Ruling

The petition is DENIED. The Decision dated July 22, 2015 and Resolution dated June 29, 2016 of the Court of Appeals in CA-G.R. CV No. 102671 are AFFIRMED. ECIC is ordered to pay Phoenix P865,410.00 with 12% interest per annum from November 5, 2009, P50,000 attorney's fees, and costs.

Ratio Decidendi

On Issue 1 (Validity of Contract of Adhesion and Waiver): Contracts of adhesion are not invalid per se but binding as ordinary contracts under Civil Code Articles 1305-1315, unless the weaker party proves imposition by dominant party depriving bargaining opportunity, as reiterated in Equitable PCI Bank v. Ng Sheung Ngor (565 Phil. 520, 536-537 (2007)) and Cabanting v. BPI (G.R. No. 201927, Feb. 17, 2016). No evidence shows ECIC or owner Ramon Encarnacion disadvantaged, uneducated, under duress, or inexperienced; presumption under jurisprudence (Spouses Poltan v. BPI, 546 Phil. 257, 269 (2007)) holds that signatories understand contents, unrebutted here. ECIC's prior three identical agreements with Phoenix (Nov. 6, 2008; Feb. 18 & 27, 2009) confirm familiarity and assent. Paragraph 15 clearly mandates claims on quality/strength at delivery, failure waiving via estoppel in pais; front page incorporates reverse terms ('No terms... except those stipulated herein and/or the reverse side thereof'), binding despite no reverse signature. ECIC's 48-day delay post-April 29, 2009 delivery and post-May 2009 City notices bolsters waiver, barring subsequent claims. Thus, refusal to pay breached obligation under Art. 1159, entitling Phoenix to payment, reduced interest (12% vice 18%), and fees. On Issue 2 (Counterclaim Denial): Rule 45 limits review to questions of law, not facts (Spouses Miano v. MERALCO, G.R. No. 205035, Nov. 16, 2016); no exceptions shown (e.g., speculation, misapprehension). Even on merits, ECIC failed evidentiary burden under Civil Code rules on obligations to prove causation: tests showed strength failure, City approved design/pre-pour, but unaccounted pouring-to-cracks period ignored; Phoenix evidenced plastic shrinkage from improper curing/evaporation (witness Engr. Villasenor). Docket fees timely per CA, but counterclaim meritless absent waiver rebuttal and causation proof. Factual calibration not for SC; record supports denial.

Main Doctrine

Contracts of adhesion, wherein one party drafts nearly all provisions and the other merely adheres by signature, are not per se invalid and are enforceable as ordinary contracts. They are only voided when the dominant party imposes terms on a weaker party deprived of equal bargaining footing, determined by peculiar circumstances and parties' situations. The presumption is that signatories understand document contents and consequences, unrebutted absent proof of illiteracy, duress, or inexperience. Clear, unambiguous terms, such as requiring claims on goods' quality at delivery, bind parties; failure to comply waives such claims via estoppel. Incorporation by reference of reverse-side terms on the signed front page renders the entire agreement binding, even without signature on all pages. Delayed notification of defects beyond reasonable time strengthens waiver conclusion. Factual causation must be proven for counterclaims alleging defective deliveries, not merely test failures, considering intervening factors like improper curing.

Access audio review, related cases, codal links, and more.

Open LexMatePH →